Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No. Cl. No. Firm T<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

y<br />

p<br />

(ii) Contractor on his part will have to employ<br />

supervisors, technicians and supporting staff in full<br />

strength commensurate with working area available.<br />

He will also arrange required materials and<br />

equipment to complete the job most expeditiously<br />

so as to ensure that the work is completed in phases<br />

within the stipulated period and to the entire<br />

satisfaction of Engineer in- charge.<br />

(iii) The Contractor is expected to have worked out<br />

a detailed programme for execution of the work well<br />

before issue of “Letter of Acceptance”, by <strong>Railway</strong><br />

and submit a Detailed Time and Activity Schedule<br />

within 30 days from issue of LoA , for the execution<br />

of work aiming at completing the entire work within<br />

the stipulated completion time. This schedule shall<br />

thereafter be approved by the Engineer-In-Charge<br />

normally within 5 working days.<br />

(iv) <strong>Railway</strong> reserves the right to modify the<br />

schedule while approving the same as well as at<br />

any stage during execution if situation so warrants.<br />

Once approved, in the event of any slippage from<br />

the time schedule especially when resulting into<br />

time over-run of the work the contractor shall submit<br />

revised schedule duly justifying the circumstances<br />

without any delay. The revised schedule shall be<br />

approved by the Engineer-In-Charge only when<br />

considered justified in his opinion otherwise it may<br />

attract penal action on the contractor as per<br />

provision of this contract.<br />

(v) The Contractor shall be held responsible for the<br />

execution of the work according to the Programme<br />

given for the execution of the work in full<br />

compliance of the approved cable route plans and<br />

also various clauses of technical specification and<br />

requirement. Failure to comply with any of these will<br />

be dealt as per provisions of GCC.<br />