Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No.<br />

81<br />

Cl. No.<br />

Chapter-4<br />

Firm<br />

Alstom<br />

T<br />

y<br />

p<br />

SSYSTEM OF QUOATING RATES<br />

SCC 4.53<br />

-The prices quoted by the <strong>Tender</strong>er shall include the<br />

F prices of materials including all incidental charges<br />

Gfor transport, loading/unloading and handling of<br />

materials, cost for arranging dispatch by rail/road<br />

direct from manufacturer‟s premises and<br />

completing all necessary formalities in all respect.<br />

The breakup of the basic cost and other taxes<br />

and duties shall be positively submitted.<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

The prices shall include all taxes, duties, Royalty<br />

land levies (including Octroi etc.) applicable to this<br />

Works Contract. Therefore, they should quote<br />

their prices taking into account the rate of sales tax<br />

as leviable in the event of sale to the Central<br />

Government Organization etc. It is clarified that<br />

required form applicable for this purpose will be<br />

supplied to the contractor, as applicable in the state<br />

where the contract is being executed. The prices<br />

shall also include provision for losses and wastage<br />

in transit and installation and commissioning. The<br />

prices quoted by the tenderer shall include cost of<br />

commissioning and testing and all costs of<br />

Administration of Contract, Insurance, Premium<br />

banker‟s charges for guarantees, cost of storage,<br />

loading-unloading and handling of materials and for<br />

any road transport which the contractor may use or<br />

carriage of materials to his depot and the site of<br />

work. The prices shall include the cost of works<br />

and adjustments necessary to be done by the<br />

contractor during or after test carried out by the<br />

purchaser.<br />

We understand that change in law, statute,<br />

tax rate etc. coming into effect after the date<br />

for submission of tender. Our understanding<br />

is that any increase/decrease in cost on<br />

account of any change in law statute, tax<br />

rate etc. or introduction of any new law,<br />

statute, tax etc. after the submission of<br />

tender shall be passed on to the Purchaser.<br />

Contractor shall provide documentary<br />

evidence of the increase or decrease to<br />

Purchaser.<br />

This Para is self explanatory and<br />

should be read in totality & <strong>Tender</strong><br />

Condition remain unchanged. Please<br />

also refer Para 4.59 of SCC.<br />

The price to be quoted by the tenderer should take into account the credit availed on inputs under the MODVAT. The tenderer should give a declaration that any let o<br />

While the price quoted in the contract are inclusive of all taxes i.e. custom duty, excise duty, octroi, local levies, Sales tax levied by any statutory authority, the purcha<br />

All taxes, duties and levies (Including octroi etc.) arising out of the transaction between the contractor and his sub contractor/supplier for this work will be included in th<br />

Arrangement of permits/license for materials will not be made by the <strong>Railway</strong> or any assistance given. The Contractor will have to make his own arrangement. Also no<br />