Subject : Pre-bid clarification on queries received from Industry Participants of TPWS: Date-30.06.2011<br />

TENDER NO. WR/S&T/HQ/2010-11/05 Virar (at Km 60)-Vadodara (at Km 397) section<br />

Sr. No.<br />

64<br />

Cl. No.<br />

Chapter-4<br />

Firm<br />

Alstom<br />

T<br />

y<br />

p<br />

GGENERAL<br />

Original Text Clarification needed Clarification of <strong>Western</strong> <strong>Railway</strong><br />

SCC 4.1<br />

(i) These regulations of tenders and contracts shall The clause specifies the priority between<br />

be read in conjunction with General Conditions of GCC and other documents. The order of<br />

Contract (GCC) with latest amendments, which shall priority within the other documents is not<br />

be subject to modifications, additions or<br />

specified. In our understanding in case of<br />

supersession by these Special Conditions of conflict between Contract<br />

Contract (SCC) and/or specifications/conditions, if documents the decreasing order of priority<br />

any, which is part of this <strong>Tender</strong> <strong>Document</strong>. shall be:<br />

This Para is self explanatory and<br />

should be read in totality.<br />

(ii) Where there is any conflict between these<br />

Special Conditions of Contract on one hand and<br />

Standard Specifications and General Conditions of<br />

Contract of <strong>Western</strong> <strong>Railway</strong> on the other hand, the<br />

former (SCC) shall prevail.<br />

(iii) Any deviations from these Special<br />

Conditions of Contract, Technical Requirement &<br />

Specifications, Schedule of Material & Supplies<br />

and/or any condition of tender document, if any,<br />

stated by the tenderer in his tender or subsequently<br />

introduced by the <strong>Railway</strong> shall be a part of the<br />

Contract only to such extent as have been<br />

explicitly accepted by the <strong>Railway</strong> and<br />

incorporated in the contract.<br />

1. Signed Agreement.<br />

2. Letter of Acceptance (with enclosures<br />

including accepted rates and agreed<br />

deviations) 3.<br />

Special Conditions of Contract 4.<br />

<strong>Tender</strong> <strong>Document</strong> (Chapter I and II ) 5.<br />

Technical Proposal 6.<br />

other documents submitted by Contractor as<br />

per ITT.<br />

7. GCC<br />

8. IRS conditions of Contract Kindly confirm<br />

our above understanding.<br />

Pre Bid Queries for TPWS 16