Segment 11: Highway 68 to Northwest School Road<br />

Along the <strong>Piedmont</strong> <strong>Greenway</strong> Trail, the Highway 68 and the proposed I-73 corridor divides the<br />

trail corridor. Because <strong>of</strong> its central location and proximity to major transportation facilities, the area surrounding<br />

NC 68 has been experiencing rapid land use development and growth. The city <strong>of</strong> Greensboro is<br />

looking at the corridor <strong>of</strong> NC 68 below Pleasant Ridge Road as a potential Scenic Corridor Overlay District.<br />

This overlay seeks to maintain the appearance <strong>of</strong> the corridor while improving travel mobility along NC 68.<br />

Because the level <strong>of</strong> NC 68 was raised to reduce the potential <strong>of</strong> flooding, there exists an opportunity<br />

to install an underpass (box-culvert) to provide trail access beneath the highway trail. An overland crossing<br />

at the road level would be feasible. However, providing a signal light on this busy road may not be possible.<br />

The existing culvert <strong>of</strong> Reedy Fork Creek where it passes under the road is not large enough for the<br />

trail. The underpass could be installed as any part <strong>of</strong> NC 68 improvements occur to accommodate the rapid<br />

growth projected for this road corridor.<br />

SEGMENT 11<br />

The proposed I-73 will be a major link between NC 68<br />

and Battleground Avenue (US 220). Reedy Fork Creek contains<br />

an ever-enlarging flood zone as you pass Alcorn Road.<br />

This area becomes a wetland that is impassable from this<br />

point north. The trail corridor will follow a small drainage<br />

channel to an existing power line east <strong>of</strong> the creek and continue<br />

north along this easement until the I-73 overpass. The<br />

corridor will pass over Reedy Fork Creek near Brigade Trail<br />

and Wesscott.<br />

The <strong>Piedmont</strong> <strong>Greenway</strong> Trail will take advantage <strong>of</strong> a<br />

small tributary that is between Northwest Middle and High<br />

Schools, and the main channel <strong>of</strong> Reedy Fork. The I-73 road<br />

alignment will require the construction <strong>of</strong> a new bridge in this<br />

area and the trail will be able to pass under the bridge. As the<br />

trail leaves the small tributaries, it will proceed south for a<br />

short distance along the north side <strong>of</strong> Northwest School Road<br />

before linking to Northwest Middle/High Schools.<br />

The trail will be a multi-use corridor that will accommodate<br />

pedestrian and biking uses. The primary trail will be<br />

10 feet wide for all users. This segment <strong>of</strong> the trail system is<br />

approximately 2.0 miles in length. One bridge will be needed<br />

to span a small drainage tributary <strong>of</strong> the main channel.<br />

Figure 20. Location <strong>of</strong> Segment 11<br />

Primary <strong>Greenway</strong> Segments<br />

Spur Trail <strong>Greenway</strong> Segments<br />

PIEDMONT GREENWAY<br />

Final <strong>Master</strong> <strong>Plan</strong> Report • 48