No. Item Qty. Unit Price Total<br />

XI. This includes segments five and six to minimize disturbance 24,678lf to 4.7 miles<br />

A. OFF ROAD FACILITIES<br />

12' Boardwalk 150 lf $170.00 $25,500.00<br />

10' Asphalt Trail 24,138 lf $35.00 $844,830.00<br />

Pedestrian Bridge (3) 90 lf $1,000.00 $90,000.00<br />

B. ON ROAD FACILITIES<br />

Crosswalks (5) 300 lf $22.00 $6,600.00<br />

Retr<strong>of</strong>it <strong>of</strong> Existing R.R tracks 1 each $10,000.00 $10,000.00<br />

C. SITE FURNISHINGS<br />

Benches 4 each $400.00 $1,600.00<br />

Bicycle Racks 2 each $500.00 $1,000.00<br />

Information Kiosk 2 each $5,000.00 $10,000.00<br />

Trash Receptacles 4 each $200.00 $800.00<br />

Bollards 18 each $250.00 $4,500.00<br />

D. SIGNAGE<br />

Mile Markers 6 each $250.00 $1,500.00<br />

Warning Signs 18 each $250.00 $4,500.00<br />

Directional 6 each $250.00 $1,500.00<br />

E. LANDSCAPING (Allowance)<br />

Reseed disturbed areas $1,000.00<br />

PHASE ELEVEN<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $960,330.00<br />

B. ON ROAD FACILITIES $16,600.00<br />

C. SITE FURNISHINGS $17,900.00<br />

D. SIGNAGE $7,500.00<br />

E. LANDSCAPING $1,000.00<br />

SUBTOTAL $1,003,330.00<br />

10% Design Fee $100,333.00<br />

15% Contingency $150,499.50<br />

GRAND TOTAL: $1,254,162.50<br />

No. Item Qty. Unit Price Total<br />

XII. <strong>Kernersville</strong> Lake Spur Trail and On Road segement from Cash Elm. School<br />

this phase does not include additions to sidewalk system 6,924lf or 1.31 miles<br />

A. OFF ROAD FACILITIES<br />

10' Asphalt Trail 6,864 lf $35.00 $240,240.00<br />

B. ON ROAD FACILITIES<br />

Crosswalks (1) 60 lf $22.00 $1,320.00<br />

C. SITE FURNISHINGS<br />

Information Kiosk 1 each $5,000.00 $5,000.00<br />

Bollards 4 each $250.00 $1,000.00<br />

D. SIGNAGE<br />

Mile Markers 2 each $250.00 $500.00<br />

Warning Signs 4 each $250.00 $1,000.00<br />

Directional 2 each $250.00 $500.00<br />

E. LANDSCAPING (Allowance)<br />

Reseed disturbed areas $1,000.00<br />

PHASE TWELVE<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $240,240.00<br />

B. ON ROAD FACILITIES $1,320.00<br />

C. SITE FURNISHINGS $6,000.00<br />

D. SIGNAGE $2,000.00<br />

E. LANDSCAPING $1,000.00<br />

SUBTOTAL $250,560.00<br />

10% Design Fee $25,056.00<br />

15% Contingency $37,584.00<br />

GRAND TOTAL: $313,200.00<br />

Figure 39. Phase 12 Cost Estimates<br />

Figure 38. Phase 11 Cost Estimates<br />

PIEDMONT GREENWAY<br />

Final <strong>Master</strong> <strong>Plan</strong> Report 66