No. Item Qty. Unit Price Total<br />
V. <strong>Kernersville</strong> Elementary School to Civitan Park 3,288lf or 0.62 miles<br />
A. OFF ROAD FACILITIES<br />
10' Asphalt Trail 3,168 lf $35.00 $110,880.00<br />
B. ON ROAD FACILITIES<br />
Crosswalks (2) 120 lf $22.00 $2,640.00<br />
Retr<strong>of</strong>it <strong>of</strong> Existing R.R tracks 1 each $10,000.00 $10,000.00<br />
C. SITE FURNISHINGS<br />
Bollards 4 each $250.00 $1,000.00<br />
D. SIGNAGE<br />
Mile Markers 4 each $250.00 $1,000.00<br />
Warning Signs 6 each $250.00 $1,500.00<br />
Directional 4 each $250.00 $1,000.00<br />
Minor Trailhead Signs 2 each $1,750.00 $3,500.00<br />
E. LANDSCAPING (Allowance)<br />
Reseed disturbed areas $1,000.00<br />
PHASE FIVE<br />
ITEM<br />
COST<br />
A. OFF ROAD FACILITIES $110,880.00<br />
B. ON ROAD FACILITIES $12,640.00<br />
C. SITE FURNISHINGS $1,000.00<br />
D. SIGNAGE $7,000.00<br />
E. LANDSCAPING $1,000.00<br />
SUBTOTAL $132,520.00<br />
10% Design Fee $13,252.00<br />
15% Contingency $19,878.00<br />
GRAND TOTAL: $165,650.00<br />
No. Item Qty. Unit Price Total<br />
VI. East Forsyth High School to Old Hollow Road 12,444lf or 2.35 miles<br />
A. OFF ROAD FACILITIES<br />
10' Asphalt Trail 12,144 lf $35.00 $425,040.00<br />
B. ON ROAD FACILITIES<br />
Crosswalks (5) 300 lf $22.00 $6,600.00<br />
Retr<strong>of</strong>it <strong>of</strong> Existing R.R tracks 3 each $10,000.00 $30,000.00<br />
Bollards 16 each $250.00 $4,000.00<br />
C. SIGNAGE<br />
Mile Markers 2 each $250.00 $500.00<br />
Warning Signs 16 each $250.00 $4,000.00<br />
Directional 6 each $250.00 $1,500.00<br />
E. LANDSCAPING (Allowance)<br />
Reseed disturbed areas $1,000.00<br />
PHASE SIX<br />
ITEM<br />
COST<br />
A. OFF ROAD FACILITIES $425,040.00<br />
B. ON ROAD FACILITIES $40,600.00<br />
C. SIGNAGE $6,000.00<br />
D. LANDSCAPING $1,000.00<br />
SUBTOTAL $472,640.00<br />
10% Design Fee $47,264.00<br />
15% Contingency $70,896.00<br />
GRAND TOTAL: $590,800.00<br />
Figure 33. Phase 6 Cost Estimates<br />
Figure 32. Phase 5 Cost Estimates<br />
PIEDMONT GREENWAY<br />
Final <strong>Master</strong> <strong>Plan</strong> Report 63