COST ESTIMATE FROM SALEM LAKE & LINVILLE ROAD TO LAKE HIGGINS MARINA<br />

PHASE I, II, III, IV, V, VI, VII, VIII, VIIII, X, XI, XII, XIII<br />

No. Item Qty. Unit Price Total<br />

I. Linville Rd. (Salem Lake) to West Mountain Street 8,020 lf or 1.52 miles<br />

A. OFF ROAD FACILITIES<br />

12' Boardwalk 200 lf $170.00 $34,000.00<br />

10' Asphalt Trail 7,520 lf $35.00 $263,200.00<br />

10' Concrete Trail 200 lf $70.00 $14,000.00<br />

B<br />

SITE FURNISHINGS<br />

Benches 2 each $400.00 $800.00<br />

Bicycle Racks 2 each $250.00 $500.00<br />

Information Kiosk w/tables 2 each $3,500.00 $7,000.00<br />

Trash Receptacles 2 each $200.00 $400.00<br />

Bollards 6 each $250.00 $1,500.00<br />

C. ELECTRICAL<br />

Phones 1 each $3,500.00 $3,500.00<br />

lighting for box-culvert 4 each $1,800.00 $7,200.00<br />

D. SIGNAGE<br />

Mile Markers 2 each $250.00 $500.00<br />

Warning Signs 4 each $250.00 $1,000.00<br />

Directional 4 each $250.00 $1,000.00<br />

Educational 1 each $2,000.00 $2,000.00<br />

Minor Trailhead Signs 2 each $1,750.00 $3,500.00<br />

E. STRUCTURAL<br />

Business I-40 Box Culvert Retro<br />

by others<br />

Concrete Ramps either side 100 lf $70.00 $7,000.00<br />

Safety Railing 40 lf $40.00 $1,600.00<br />

F. LANDSCAPING (Allowance)<br />

Reseed disturbed areas along School property $1,000.00<br />

PHASE ONE<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $311,200.00<br />

B. SITE FURNISHINGS $10,200.00<br />

C. ELECTRICAL $10,700.00<br />

D. SIGNAGE $8,000.00<br />

E. STRUCTURAL $8,600.00<br />

F. LANDSCAPING $1,000.00<br />

SUBTOTAL $349,700.00<br />

10% Design Fee $34,970.00<br />

15% Contingency $52,455.00<br />

GRAND TOTAL: $437,125.00<br />

No. Item Qty. Unit Price Total<br />

II. Lake Higgins TH and ends at Pleasant Ridge Road TH 10,624 lf or 2.1 miles<br />

A. OFF ROAD FACILITIES<br />

12' Boardwalk 300 lf $170.00 $51,000.00<br />

10' concrete Trail 200 lf $70.00 $14,000.00<br />

10' Asphalt Trail 10,032 lf $35.00 $351,120.00<br />

12' wide Pedestrian Bridge 50 lf $1,000.00 $50,000.00<br />

10' Asphalt Connector Trail 300 lf $35.00 $10,500.00<br />

B. ON ROAD FACILITIES<br />

Minor TrailHead Pleasant Ridge Road<br />

Crosswalks 60 lf $22.00 $1,320.00<br />

Route Signage 1 each $250.00 $250.00<br />

Access Road to Parking area 20lf X32lf $3,500.00<br />

10-car gravel parking lot $32,000.00<br />

C. SITE FURNISHINGS<br />

Benches 1 each $400.00 $400.00<br />

Bicycle Racks 2 each $500.00 $1,000.00<br />

Information Kiosk w/tables 1 each $3,500.00 $3,500.00<br />

Trash Receptacles 1 each $100.00 $100.00<br />

Bollards 2 each $250.00 $500.00<br />

D. ELECTRICAL<br />

Lighting Under Bridge 2 each $1,800.00 $3,600.00<br />

Phones 1 each $3,500.00 $3,500.00<br />

E. SIGNAGE<br />

Mile Markers 4 each $250.00 $1,000.00<br />

Warning Signs 2 each $250.00 $500.00<br />

Directional 6 each $250.00 $1,500.00<br />

Educational 3 each $2,000.00 $6,000.00<br />

Minor Trailhead Signs 1 each $1,750.00 $1,750.00<br />

F. LANDSCAPING (Allowance)<br />

Reseed disturbed areas along School property $1,000.00<br />

PHASE TWO<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $476,620.00<br />

B. ON ROAD FACILITIES $37,070.00<br />

C. SITE FURNISHINGS $5,500.00<br />

D. ELECTRICAL $7,100.00<br />

E. SIGNAGE $10,750.00<br />

F. LANDSCAPING $1,000.00<br />

SUBTOTAL $537,040.00<br />

10% Design Fee $53,704.00<br />

15% Contingency $80,556.00<br />

GRAND TOTAL: $671,300.00<br />

Figure 28. Phase 1 Cost Estimates<br />

Figure 29. Phase 2 Cost Estimates<br />

PIEDMONT GREENWAY<br />

Final <strong>Master</strong> <strong>Plan</strong> Report 61