No. Item Qty. Unit Price Total<br />

VIIII. Reedy Fork Creek to Highway 68. 13,818lf or 2.60 miles<br />

A. OFF ROAD FACILITIES<br />

Pedestrian crossing at Hwy 68 to be determined by others (box culvert or at grade crossing)<br />

10' Asphalt Trail 13,728 lf $35.00 $480,480.00<br />

Pedestrian Bridge (1) 30 lf $1,000.00 $30,000.00<br />

B. ON ROAD FACILITIES<br />

Crosswalks (1) 60 lf $22.00 $1,320.00<br />

C. SITE FURNISHINGS<br />

Bollards 4 each $250.00 $1,000.00<br />

D. SIGNAGE<br />

Mile Markers 2 each $250.00 $500.00<br />

Warning Signs 4 each $250.00 $1,000.00<br />

Directional 2 each $250.00 $500.00<br />

E. LANDSCAPING (Allowance)<br />

Reseed disturbed areas $1,000.00<br />

PHASE NINE<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $510,480.00<br />

B. ON ROAD FACILITIES $1,320.00<br />

C. SITE FURNISHINGS $1,000.00<br />

D. SIGNAGE $2,000.00<br />

E. LANDSCAPING $1,000.00<br />

SUBTOTAL $515,800.00<br />

10% Design Fee $51,580.00<br />

15% Contingency $77,370.00<br />

GRAND TOTAL: $644,750.00<br />

Figure 36. Phase 9 Cost Estimates<br />

No. Item Qty. Unit Price Total<br />

X. Highway 68 to Northwest School Rd. 10,740lf or 2.0 miles<br />

A. OFF ROAD FACILITIES<br />

12' Boardwalk 100 lf $170.00 $17,000.00<br />

10' Asphalt Trail 10,460 lf $35.00 $366,100.00<br />

Pedestrian Bridge (2) 60 lf $1,000.00 $60,000.00<br />

B. ON ROAD FACILITIES<br />

Crosswalks (2) 120 lf $22.00 $2,640.00<br />

C. SITE FURNISHINGS<br />

Benches 2 each $400.00 $800.00<br />

Bicycle Racks 1 each $500.00 $500.00<br />

Information Kiosk 1 each $5,000.00 $5,000.00<br />

Trash Receptacles 2 each $200.00 $400.00<br />

Bollards 8 each $250.00 $2,000.00<br />

D. SIGNAGE<br />

Mile Markers 2 each $250.00 $500.00<br />

Warning Signs 4 each $250.00 $1,000.00<br />

Directional 2 each $250.00 $500.00<br />

E. LANDSCAPING (Allowance)<br />

Reseed disturbed areas $1,000.00<br />

PHASE TEN<br />

ITEM<br />

COST<br />

A. OFF ROAD FACILITIES $443,100.00<br />

B. ON ROAD FACILITIES $2,640.00<br />

C. SITE FURNISHINGS $8,700.00<br />

D. SIGNAGE $2,000.00<br />

E. LANDSCAPING $1,000.00<br />

SUBTOTAL $457,440.00<br />

10% Design Fee $45,744.00<br />

15% Contingency $68,616.00<br />

GRAND TOTAL: $571,800.00<br />

Figure 37. Phase 10 Cost Estimates<br />

PIEDMONT GREENWAY<br />

Final <strong>Master</strong> <strong>Plan</strong> Report 65