No. Item Qty. Unit Price Total<br />
VII. Old Hollow Rd. to YMCA 8,220lf or 1.56 miles<br />
A. OFF ROAD FACILITIES<br />
10' Asphalt Trail 7,920 lf $35.00 $277,200.00<br />
B. ON ROAD FACILITIES<br />
Crosswalks (5) 300 lf $22.00 $6,600.00<br />
Retr<strong>of</strong>it <strong>of</strong> Existing R.R tracks 1 each $10,000.00 $10,000.00<br />
C. SITE FURNISHINGS<br />
Bollards 14 each $250.00 $3,500.00<br />
C. SIGNAGE<br />
Warning Signs 14 each $250.00 $3,500.00<br />
Directional 6 each $250.00 $1,500.00<br />
Minor Trailhead Signs 1 each $1,750.00 $1,750.00<br />
Mile Markers 2 each $250.00 $500.00<br />
E. LANDSCAPING (Allowance)<br />
Reseed disturbed areas $1,000.00<br />
PHASE SEVEN<br />
ITEM<br />
COST<br />
A. OFF ROAD FACILITIES $277,200.00<br />
B. ON ROAD FACILITIES $16,600.00<br />
C. SITE FURNISHINGS $3,500.00<br />
D. SIGNAGE $7,250.00<br />
E. LANDSCAPING $1,000.00<br />
SUBTOTAL $305,550.00<br />
10% Design Fee $30,555.00<br />
15% Contingency $45,832.50<br />
GRAND TOTAL: $381,937.50<br />
Figure 34. Phase 7 Cost Estimates<br />
No. Item Qty. Unit Price Total<br />
VIII. Triad Park to Reedy Fork Creek 7,154lf or 1.35 miles<br />
A. OFF ROAD FACILITIES<br />
12' Boardwalk 200 lf $170.00 $34,000.00<br />
10' Asphalt Trail 6,864 lf $35.00 $240,240.00<br />
Pedestrian Bridge (1) 30 lf $1,000.00 $30,000.00<br />
B. ON ROAD FACILITIES<br />
Crosswalks (2) 120 lf $22.00 $2,640.00<br />
C. SITE FURNISHINGS<br />
Bollards 6 each $250.00 $1,500.00<br />
D. SIGNAGE<br />
Mile Markers 2 each $250.00 $500.00<br />
Warning Signs 6 each $250.00 $1,500.00<br />
Directional 2 each $250.00 $500.00<br />
Minor Trailhead Signs 1 each $1,750.00 $1,750.00<br />
E. LANDSCAPING (Allowance)<br />
Reseed disturbed areas $1,000.00<br />
PHASE EIGHT<br />
ITEM<br />
COST<br />
A. OFF ROAD FACILITIES $304,240.00<br />
B. ON ROAD FACILITIES $2,640.00<br />
C. SITE FURNISHINGS $1,500.00<br />
D. SIGNAGE $5,250.00<br />
E. LANDSCAPING $1,000.00<br />
SUBTOTAL $314,630.00<br />
10% Design Fee $31,463.00<br />
15% Contingency $47,194.50<br />
GRAND TOTAL: $393,287.50<br />