13.07.2015 Views

bangladesh power development board tender document for ... - BPDB

bangladesh power development board tender document for ... - BPDB

bangladesh power development board tender document for ... - BPDB

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

initial commercial operation (ICO) as guaranteed in Schedule-A [Guarantee], Vol. 3of 3 applicable <strong>for</strong> the plant. Further, should the plant or the equipment furnishedby the Contractor fails to meet the specified Per<strong>for</strong>mance Guarantee stipulated inrespective Technical Requirements and Technical Particulars then the Contractorshall pay to the Board the Liquidated Damages computed in accordance with theprovisions of the Clause 30.0 of Chapter III, Special Conditions.To determine the LIQUIDATED DAMAGES <strong>for</strong> the delayed completion of ICO, thetotal contract price of the plant shall be considered.For early completion of the contract, Tenderer shall be rewarded at the rate of0.025% of contract price <strong>for</strong> each calendar day, which will not exceed 2.5% of theContract Price.In the matter of assessment of Liquidated Damages on account of failure toachieve guaranteed <strong>power</strong> output/heat rate and failure to complete the specifiedsupply and/or work within the period of time stipulated in Contract, considerationshall be made <strong>for</strong> the plant and Liquidated Damages assessed as per terms of theContract.The Board shall have the right to deduct any unpaid Liquidated Damages from anymonies in its hands or otherwise due, or to become due, to the Contractor, or tosue <strong>for</strong> and recover compensation <strong>for</strong> such Liquidated Damages includingencashment of the Per<strong>for</strong>mance Security.The payment by the Contractor of the Liquidated Damages is in lieu of all otherliabilities to the Board <strong>for</strong> damages arising from delays and the ceiling of LiquidatedDamages expressed constitute the ceiling of the Contractor's liability <strong>for</strong> delay incompletion of the Work, and beyond this ceiling the Contract can be terminatedunder the provision of this Contract.46.0 HINDRANCES AND DELAYSIn executing the Contract, the Contractor expressly covenants and agrees that . inundertaking to complete the Work within the time therein fixed, he has taken intoconsideration and made allowances <strong>for</strong> all hindrances and delays incident to suchWork, whether growing out of delays in securing materials or workmen orotherwise. No charge shall be made by the Contractor <strong>for</strong> hindrances or delaysfrom any cause during the progress of the Work, or any portion thereof, embracedin this Contract.47.0 EXTENSION OF TIMEShould the Contractor be delayed in the final completion of the Work by any causeor causes outside of and beyond the control of the Contractor, such as but notlimited to acts of the public enemy, war, blockades. insurrections, riots, epidemics,civil disturbances, strikes, fire, and other causes not within the control of theContractor, including acts of the Board, which makes the per<strong>for</strong>mance of theContract unfeasible and which by the exercise of due diligence the Contractor inper<strong>for</strong>mance of the Contract is unable to overcome, then an extension of timesufficient to compensate <strong>for</strong> the delay, as recommended by the Engineer, shall begranted by the Board and the Contractor shall not be charged with LiquidatedDamages <strong>for</strong> such delay; provided, however, that the Contractor shall give theBoard and the Engineer notice in writing of the cause of delay in each case within87

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!