<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong> Status Report <strong>of</strong> Projects Exceeding $5.0 Million<br />

for period January 1, 2008 - June 30, 2008<br />

Contract Status<br />

State <strong>of</strong><br />

Approved<br />

Campus / Project and Date<br />

Construction<br />

Budget Categories Amount<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong> Architect: Various Percent <strong>of</strong> Funds Expended: NA 309 Proj (Under $500,000) $3,533,120.00<br />

Deferred Maintenance - LB309 / LB 1100 UBRAF Contract Date: Various Substantial Completion Date: NA UBRAF Proj (Under $500,000) 1557490.00<br />

Method <strong>of</strong> Construction: Various Campus Co-Funds 1456892.00<br />

General Contractor: Various $6,547,502.00<br />

Contract Date: Various<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong> at Kearney Architect: Sinclair Hille Architects Percent <strong>of</strong> Funds Expended: 83% 1. Construction Budget $20,015,906.00<br />

Student Housing Project Contract Date: 09/01/05 Substantial Completion Date: July 31, 2007 & 2. Non Construction Budget 1764094.00<br />

(New Residence Hall) Method <strong>of</strong> Construction: Construction Manager/GMP (August 12, 2008) Total Project Cost $21,780,000.00<br />

General Contractor: Sampson Construction<br />

Contract Date: May 19, 2006<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong> at Kearney Architect: LEO A DALY Percent <strong>of</strong> Funds Expended: 31% 1. Construction Budget $16,900,000.00<br />

Central Utility Plant & System Contract Date: March 9, 2007 Substantial Completion Date: (July 26, 2009) 2. Non Construction Budget 1560000.00<br />

Method <strong>of</strong> Construction: Construction Manager/GMP Total Project Cost $18,460,000.00<br />

General Contractor: JE Dunn<br />

Contract Date: July 12, 2007<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong> at Kearney Architect: The Clark Enersen Partners Percent <strong>of</strong> Funds Expended: 15% 1. Construction Budget $12,062,000.00<br />

Bruner Hall <strong>of</strong> Science - Phase II Contract Date: August 6, 2007 Substantial Completion Date: (December 2009) 2. Non Construction Budget 2490000.00<br />

Method <strong>of</strong> Construction: Construction Manager/GMP Total Project Cost $14,552,000.00<br />

General Contractor: Beckenhauer Construction Inc.<br />

Contract Date: August 23, 2007<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong>-Lincoln Architect: Davis Design Percent <strong>of</strong> Funds Expended: 74% 1. Construction Budget $9,163,798.00<br />

Othmer Hall: cGMP Pilot Plant Contract Date: January 26, 2004 Substantial Completion Date: June 18, 2008 2. Non Construction Budget 2447821.00<br />

(Finishing <strong>of</strong> Basement Shell Space) Method <strong>of</strong> Construction: Construction Manager/GMP Total Project Cost $11,611,619.00<br />

General Contractor: Hawkins Construction<br />

Contract Date: December 20, 2007<br />

<strong>University</strong> <strong>of</strong> <strong>Nebraska</strong>-Lincoln Architect: Lockwood Greene Percent <strong>of</strong> Funds Expended: 97% 1. Construction Budget $18,582,080.00<br />

Ken Morrison Life Sciences Research Center Contract Date: August 1, 2004 Substantial Completion Date: February 29, 2008 2. Non Construction Budget 2561920.00<br />

(<strong>Nebraska</strong> Center for Virology) Method <strong>of</strong> Construction: Conventional Bidding Total Project Cost $21,144,000.00<br />

General Contractor: Sampson Const. Co.<br />

Contract Date: October 27, 2006