Schedule:<br />

Environmental Document Approval Date: Pending Approval<br />

Municipal Consent Approval Date: Pending Approval<br />

Geometric Layout Approval Date: Pending Approval<br />

Construction Limits Established Date: Pending Approval<br />

Original Letting Date: 11/01/2015<br />

Current Letting Date: 11/17/2017<br />

Construction Season: 2018-2019<br />

Estimated Substantial Completion: 08/01/2019<br />

Project History:<br />

Rehabilitate or replace Mn/DOT Bridge 4700 over<br />

the Red River between <strong>Minnesota</strong> and North<br />

Dakota. Completed bridge will include improved<br />

access for pedestrians and bicyclists. If a new<br />

bridge is constructed the length and alignment will<br />

need to closely match the existing conditions due<br />

to proximity of downtown businesses and in-place<br />

flood protection facilities. The existing bridge is<br />

600 feet long.<br />

Project Benefits:<br />

Upgrading or replacement of a fracture critical<br />

structure will provide continued inter-state access<br />

in a metropolitan area.<br />

Project Risks:<br />

Need to coordinate project scheduling with<br />

emergency services, schools and transit. Bridge<br />

4700 is one of 24 historic bridges Mn/DOT has<br />

committed to the FHWA to preserve. Proximity to<br />

downtown business and inplace flood protection<br />

limits bridge profile. Seasonal flooding of Red<br />

River may provide construction difficulties.<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

PROJECT SUMMARY<br />

Hwy. 2<br />

US 2B over Red River in East Grand Forks (Sorlie)<br />

Bridge 4700<br />

<strong>State</strong> Project No. 6015-07<br />

Project Description:<br />

Remove and replace bridge 4700 with new<br />

structurally redundant bridge. Bridge will<br />

include improved access for pedestrians and<br />

bicyclists. Current bridge length is<br />

approximately 600 feet, new bridge length<br />

will be very similar due to proximity of<br />

downtown.<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Construction Letting:<br />

Other Construction Elements:<br />

Engineering:<br />

Right of Way:<br />

Recent Changes and Updates:<br />

9090<br />

RED R<br />

4700<br />

East Grand Forks<br />

Polk<br />

North Dakota DOT is the lead agency. The district needs more time for project<br />

development because the bridge is a historic structure and the alternative of rehabilitation<br />

instead of replacement requires more evaluation time.<br />

Key Cost Estimate Assumptions:<br />

Baseline Est. Current Est.<br />

29.0<br />

6.0<br />

9.5<br />

1.4<br />

Total: $ 45.9 - $<br />

Safety will be improved as a result of eliminating the current fracture critical structure,<br />

pedestrian/bicycle access will be improved<br />

$<br />

$<br />

$<br />

$<br />

- $<br />

- $<br />

- $<br />

- $<br />

50.6<br />

0.0<br />

9.5<br />

1.4<br />

61.5<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 2<br />

3920 Highway 2 West<br />

(218) 755-6500<br />

District Engineer: Lynn C. Eaton<br />

Project Manager: J.T. Anderson<br />

Original date of Posting: Jan 2009<br />

Revised Date: 1/15/2011<br />

17<br />