Schedule:<br />
Environmental Document Approval Date: Anticipated Jan 20<br />
Municipal Consent Approval Date: Not Needed<br />
Geometric Layout Approval Date: Dec-10<br />
Construction Limits Established Date: Dec-10<br />
Original Letting Date: 01/24/2012<br />
Current Letting Date: 2/24/2012<br />
Construction Season: 2012-14<br />
Estimated Substantial Completion:<br />
Project History:<br />
Bridge 9320 was built in 1967.<br />
Project Benefits:<br />
Dresbach Bridge over Mississippi River (Dresbach)<br />
Bridge 9320<br />
<strong>State</strong> Project No. 8580-149<br />
http://www.dot.state.mn.us/d6/projects/dresbachbridge/<br />
Bridge 9320 was built in 1967 and is near the end<br />
of its life expectancy. Bridge 9320 is fracture<br />
critical, meaning that if one of the critical members<br />
of the bridge fails, the entire structure could fail.<br />
Project Risks:<br />
The close proximity of this bridge to Trunk<br />
Highway 61, the railroad tracks and the <strong>Minnesota</strong><br />
Rest Area, will make the roadway and bridge<br />
geometry challenging. There will be numerous<br />
environmental permits required.<br />
Annual Report on Major Highway Projects<br />
<strong>Minnesota</strong> Department of Transportation<br />
PROJECT SUMMARY<br />
I 90<br />
Project Description:<br />
Replace Bridge 9320 and the roadway<br />
approaches on the <strong>Minnesota</strong> and<br />
Wisconsin sides. Improvements to the<br />
Dresbach Rest Area are not included in the<br />
project scope.<br />
Total Project Cost Estimate (millions)<br />
Date in which the project entered into the STIP:<br />
Recent Changes and Updates:<br />
29<br />
1<br />
90<br />
Winona<br />
La Crescent<br />
Houston<br />
12/21/2009<br />
Baseline Est. Current Est.<br />
Construction Letting: $ 256.5<br />
$ 166.0<br />
Other Construction Elements: $ 0.0<br />
$ 0.0<br />
Engineering: $ 28.1<br />
$ 32.1<br />
Right of Way: $ 0.0<br />
$ 0.0<br />
Total: $ 284.6 $ 198.1<br />
Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />
OCPPM.<br />
As the risks for the projects are identified and are mitigated, the cost estimate is reduced.<br />
Key Cost Estimate Assumptions:<br />
Environmental impacts with bridge and roadway approach work are not significant. US Fish<br />
and wildlife services agrees to Right of Way swap.<br />
<strong>Minnesota</strong> Department of Transportation<br />
District 6<br />
2900 48th Street NW<br />
(507) 286-7500<br />
District Engineer: Nelrae Succio<br />
Project Manager: Craig Falkum<br />
Original date of Posting: Jan 2009<br />
Revised Date: 1/15/2011<br />