Schedule:<br />

Environmental Document Approval Date: Anticipated Jan 20<br />

Municipal Consent Approval Date: Not Needed<br />

Geometric Layout Approval Date: Dec-10<br />

Construction Limits Established Date: Dec-10<br />

Original Letting Date: 01/24/2012<br />

Current Letting Date: 2/24/2012<br />

Construction Season: 2012-14<br />

Estimated Substantial Completion:<br />

Project History:<br />

Bridge 9320 was built in 1967.<br />

Project Benefits:<br />

Dresbach Bridge over Mississippi River (Dresbach)<br />

Bridge 9320<br />

<strong>State</strong> Project No. 8580-149<br />

http://www.dot.state.mn.us/d6/projects/dresbachbridge/<br />

Bridge 9320 was built in 1967 and is near the end<br />

of its life expectancy. Bridge 9320 is fracture<br />

critical, meaning that if one of the critical members<br />

of the bridge fails, the entire structure could fail.<br />

Project Risks:<br />

The close proximity of this bridge to Trunk<br />

Highway 61, the railroad tracks and the <strong>Minnesota</strong><br />

Rest Area, will make the roadway and bridge<br />

geometry challenging. There will be numerous<br />

environmental permits required.<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

PROJECT SUMMARY<br />

I 90<br />

Project Description:<br />

Replace Bridge 9320 and the roadway<br />

approaches on the <strong>Minnesota</strong> and<br />

Wisconsin sides. Improvements to the<br />

Dresbach Rest Area are not included in the<br />

project scope.<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Recent Changes and Updates:<br />

29<br />

1<br />

90<br />

Winona<br />

La Crescent<br />

Houston<br />

12/21/2009<br />

Baseline Est. Current Est.<br />

Construction Letting: $ 256.5<br />

$ 166.0<br />

Other Construction Elements: $ 0.0<br />

$ 0.0<br />

Engineering: $ 28.1<br />

$ 32.1<br />

Right of Way: $ 0.0<br />

$ 0.0<br />

Total: $ 284.6 $ 198.1<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

As the risks for the projects are identified and are mitigated, the cost estimate is reduced.<br />

Key Cost Estimate Assumptions:<br />

Environmental impacts with bridge and roadway approach work are not significant. US Fish<br />

and wildlife services agrees to Right of Way swap.<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 6<br />

2900 48th Street NW<br />

(507) 286-7500<br />

District Engineer: Nelrae Succio<br />

Project Manager: Craig Falkum<br />

Original date of Posting: Jan 2009<br />

Revised Date: 1/15/2011<br />

9320<br />

Page E9