Schedule:<br />

Environmental Document Approval Date: Pending Approval<br />

Municipal Consent Approval Date: Not Needed<br />

Geometric Layout Approval Date: Not Needed<br />

Construction Limits Established Date: Not Needed<br />

Original Letting Date: 11/17/2017<br />

Current Letting Date: 11/20/2015<br />

Construction Season: 2016<br />

Estimated Substantial Completion: 09/01/2016<br />

Project History:<br />

The expectation of this project is that Bridge 9090<br />

will be rehabilitated to address some of its<br />

currently deficient features. This structure was<br />

built in 1963 and is still very structurally sound.<br />

Pier repairs, pigeon abatement, a new paint<br />

system and a new deck will all be a part of this<br />

project.<br />

Project Benefits:<br />

Replace current lead based paint system with a<br />

new, more environmentally friendly one, improve<br />

pigeon abatement entities to increase safety to<br />

bridge workers and facilitate easier inspection of<br />

critical members, improve ride quality<br />

Project Risks:<br />

Need to coordinate project scheduling with<br />

emergency services, schools and transit, pier on<br />

ND side may need to be replaced if their project to<br />

stabilities it in 2010 is unsuccessful, several<br />

agencies involved in decision-making/approval<br />

process<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

PROJECT SUMMARY<br />

Hwy. 2<br />

Kennedy Bridge in East Grand Forks (Kennedy)<br />

Bridge 9090<br />

<strong>State</strong> Project No. 6018-02<br />

Project Description:<br />

Rehabilitate existing Bridge 9090 including<br />

enhanced pigeon abatement, new paint<br />

system and new bridge deck.<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Construction Letting:<br />

Other Construction Elements:<br />

Engineering:<br />

Right of Way:<br />

Recent Changes and Updates:<br />

Polk<br />

2<br />

RED R<br />

East Grand Forks<br />

Prior to the Chapter 152 funding, a bridge painting project was programmed for 2009. With<br />

the addition of this additional funding, more extensive rehabilitation work is now<br />

programmed for 2016 to include painting, deck and pier rehabilitation.<br />

Key Cost Estimate Assumptions:<br />

Baseline Est. Current Est.<br />

9.0<br />

0.0<br />

2.4<br />

0.0<br />

Total: $ 11.4 - $<br />

Structure life and integrity of its members will be enhanced considerably by this work.<br />

$<br />

$<br />

$<br />

$<br />

- $<br />

- $<br />

- $<br />

- $<br />

15.0<br />

0.0<br />

2.4<br />

0.0<br />

17.4<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 2<br />

3920 Highway 2 West<br />

(218) 755-6500<br />

District Engineer: Lynn C. Eaton<br />

Project Manager: J.T. Anderson<br />

Original date of Posting: Jan 2009<br />

Revised Date: 1/15/2011<br />