Schedule:<br />

Environmental Document Approval Date: Pending Approval<br />

Municipal Consent Approval Date: Not Needed<br />

Geometric Layout Approval Date: 08/06/2009<br />

Construction Limits Established Date: Pending Approval<br />

Original Letting Date: 03/27/2009<br />

Current Letting Date: (3/25/2011<br />

Construction Season: 2011<br />

Estimated Substantial Completion: 2011<br />

Project History:<br />

Project initiated by the need for regular pavement<br />

rehabilitation. Scope was broadened to include<br />

several safety improvements. [Left turn lane<br />

modifications at Design and Clearwater Drive(s),<br />

Extension of all auxiliary lanes to 500 feet, partial<br />

implementation of access management plan<br />

developed in 2001]. Installation of three left turn<br />

lanes between Nisswa and Pequot Lakes [twolane<br />

section] scoped into this project to prevent<br />

further delay of these low-cost safety<br />

improvements.<br />

Project Benefits:<br />

Improved Safety and Reduced Congestion<br />

Project Risks:<br />

Closing 20+ median crossovers may become<br />

controversial. Section 4(f) property involved at one<br />

left turn lane location.<br />

Annual Report on Major Highway Projects<br />

<strong>Minnesota</strong> Department of Transportation<br />

PROJECT SUMMARY<br />

Hwy. 371<br />

From Design Drive in Baxter to Nisswa<br />

<strong>State</strong> Project No. 1810-95<br />

Project Description:<br />

Mill and overlay existing 4-lane section of<br />

Hwy 371 from Baxter to Nisswa. Improve left<br />

turn lanes at Clearwater and Design Drive(s).<br />

Install new dedicated left turn lanes at 3<br />

locations between Nisswa and Pequot<br />

Lakes. Partial implementation of access<br />

management plan developed in 2001.<br />

105<br />

Cass<br />

126<br />

East Gull Lake<br />

Total Project Cost Estimate (millions)<br />

Date in which the project entered into the STIP:<br />

Recent Changes and Updates:<br />

125<br />

Nisswa<br />

115<br />

77<br />

Crow Wing<br />

Baseline Est. Current Est.<br />

Construction Letting: $ 10.8<br />

$ 10.8<br />

Other Construction Elements: $ 0.5<br />

$ 0.5<br />

Engineering: $ 2.0<br />

$ 2.0<br />

Right of Way: $ 0.0<br />

$ 0.0<br />

The delay of SP 1810-92 resulted in a re-scope of this project including three left turn lanes<br />

being added in the segment where the four-lane project (SP 1810-92) will be built as an<br />

interim fix to address safety concerns. This added cost and complexity<br />

Key Cost Estimate Assumptions:<br />

No purchase of R/W needed. No extensive mitigation required for impact to section 4(f)<br />

property [Only requires permit from the DNR]<br />

Baxter<br />

Total: $ 13.3 $ 13.3<br />

146<br />

49<br />

127<br />

5<br />

Brainerd<br />

Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />

OCPPM.<br />

<strong>Minnesota</strong> Department of Transportation<br />

District 3<br />

7694 Industrial Park Road<br />

(218) 828-5700<br />

District Engineer: Robert Busch<br />

Project Manager: Jim Hallgren<br />

Original date of Posting: Jan 2009<br />

Revised Date: 1/15/2011<br />

20<br />

48<br />

Page C8