Schedule:<br />
Environmental Document Approval Date: Pending Approval<br />
Municipal Consent Approval Date: Pending Approval<br />
Geometric Layout Approval Date: Pending Approval<br />
Construction Limits Established Date: Pending Approval<br />
Original Letting Date: 11/17/2017<br />
Current Letting Date: 11/17/2017<br />
Construction Season: 2018-2019<br />
Estimated Substantial Completion: 08/01/2019<br />
Project History:<br />
This Pennsylvania Steel High Truss bridge with an<br />
open grate bridge deck was constructed in 1959<br />
by the City of Baudette and operated as a toll<br />
bridge until Mn/DOT and Ontario Ministry of<br />
Transportation assumed ownership. The deck<br />
width is 26.5 feet, the main span length is 192.5<br />
feet with the structure length being 1,285 feet.<br />
Project Benefits:<br />
Upgrading or replacement of a fracture critical<br />
structure will improve geometry and traffic safety<br />
while proving continued international access.<br />
Project Risks:<br />
Possible relocation or modifications of US and<br />
Canadian Customs buildings and a transfer station<br />
which serves power to the cities of Baudette and<br />
Rainy River, Ontario, Canada. - cultural resource<br />
issues in <strong>Minnesota</strong> as well as Ontario, Canada. -<br />
international agreements will need to be developed<br />
and coordinated to enable budget and logistics<br />
planning.<br />
Annual Report on Major Highway Projects<br />
<strong>Minnesota</strong> Department of Transportation<br />
PROJECT SUMMARY<br />
Hwy. 72<br />
Rainy River Bridge in Baudette<br />
Bridge 9412<br />
<strong>State</strong> Project No. 3905-09<br />
Project Description:<br />
Rehabilitation or Replacement of Mn/DOT<br />
Bridge 9412 over the Rainy River.<br />
Total Project Cost Estimate (millions)<br />
Date in which the project entered into the STIP:<br />
Recent Changes and Updates:<br />
73<br />
39<br />
3<br />
1<br />
5<br />
22<br />
35<br />
26<br />
27<br />
9412<br />
Baudette<br />
Lake of the Woods<br />
Baseline Est. Current Est.<br />
Construction Letting: $ 42.0<br />
$ 42.0<br />
Other Construction Elements: $ 2.1<br />
$ 2.1<br />
Engineering: $ 8.4<br />
$ 8.4<br />
Right of Way: $ 10.0<br />
$ 10.0<br />
Total: $ 62.5 $ 62.5<br />
Construction cost estimates are adjusted to the mid-year of construction, using inflation rates provided by<br />
OCPPM.<br />
During winter 2010/2011 a preliminary study will be done to evaluate bridge options and<br />
also evaluate rehabilitation options.<br />
Key Cost Estimate Assumptions:<br />
Safety will be improved as a result of eliminating the current fracture critical structure and<br />
improving geometry.<br />
<strong>Minnesota</strong> Department of Transportation<br />
District 2<br />
3920 Highway 2 West<br />
(218) 755-6500<br />
District Engineer: Lynn C. Eaton<br />
Project Manager: Phil Bergem<br />
Original date of Posting: Jan 2009<br />
Revised Date: 1/15/2011<br />
19<br />
Page B8