19.06.2014 Views

DIGEST 2006 - Sabita

DIGEST 2006 - Sabita

DIGEST 2006 - Sabita

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

intensive and time consuming<br />

projects such as deep patch<br />

maintenance are even more<br />

troublesome.<br />

A deep patch maintenance project<br />

in Sydney, Australia, required that<br />

a stretch of road pavement 67<br />

meters long, approximately<br />

400mm deep and 3 meters wide<br />

be removed, profiled and repaved<br />

in four layers within 9 hours —<br />

working at night, in the middle of<br />

winter. No rutting was to be<br />

observed the next morning or<br />

shortly thereafter as a result of<br />

elevated asphalt temperatures.<br />

The road carries a traffic loading of<br />

approximately 60 000 vehicles/<br />

day, and road authority<br />

specifications on compaction, ride<br />

quality etc. had to be met.<br />

Project<br />

requirements<br />

The project<br />

requirements could<br />

only be achieved by<br />

producing and<br />

delivering “warm<br />

mix” asphalt to site,<br />

and laying it at<br />

considerably lower<br />

temperatures than<br />

normal. This was achieved by<br />

modifying the bitumen with FT<br />

wax at 1.5% of the binder<br />

content.<br />

The project started at 20h30 with<br />

the profiling and removing of the<br />

old asphalt and base layers. Once<br />

the area had been cleaned,<br />

200mm of stabilised base was<br />

compacted into the affected area<br />

and finished to ensure that exact<br />

levels were attained. This process<br />

No extraordinary<br />

precautions<br />

were taken<br />

during the<br />

paving or<br />

compaction<br />

processes<br />

lasted until approximately 00h30,<br />

by which time the ambient<br />

temperature had dropped to 10 0 C.<br />

Wind chill effects made workability<br />

and effective compaction even<br />

more difficult.<br />

The asphalt was to be laid in two<br />

base layers of 60mm each, and<br />

two wearing course layers of<br />

45mm each. The 60mm base<br />

layers were produced at 130 0 C,<br />

and the two top layers at 140 0 C.<br />

Paving of the first layer began at<br />

approximately 00h45. In addition<br />

to the low paving temperatures,<br />

the paver burners were also<br />

limited to 120 0 C to minimise<br />

introduction of any extra heat into<br />

the system.<br />

Temperature probes were inserted<br />

into the core of<br />

each asphalt layer<br />

to measure<br />

variations in the<br />

temperature of each<br />

mat throughout the<br />

whole process. The<br />

probes were placed<br />

in the middle of<br />

each layer (probe 1<br />

in the bottom and 4<br />

in the top layers)<br />

and not directly on<br />

top of each other to<br />

make sure that the wires were not<br />

cut during the rolling. The<br />

temperature increase is due to the<br />

subsequent layers being deposited<br />

on top of the underlying<br />

layers.The detailed temperature<br />

profiles in Figure 3 show the core<br />

start temperatures and the time<br />

frames taken to finish all four<br />

layers.<br />

91

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!