These effects are presented in order of importance. Damage that<br />
affects carrying capacity, will there<strong>for</strong>e be given higher priority<br />
than that affecti ng environment or maintenance costs.<br />
When relevant, the cost of repairs shall also include traffic costs as<br />
wei l.<br />
One damage may have several consequences.<br />
Assessment of Damage by<br />
Combining Degree and<br />
Consequence of Damage<br />
Damage that affects the<br />
Carrying Capacity<br />
The condition of a bridge element is assessed by cOllS idering the<br />
seriousness and effect of any damage to it. The assessment therefo<br />
re, is a combination of the degree and consequence of the damage.<br />
This combination results in the final assessment ofthc damage as<br />
outlined below:<br />
I C = Minor damage/defect that in the long run may present<br />
danger to the carrying capacity of the structure. The<br />
damage might not require repair within the coming 10<br />
years.<br />
2C = Average damage/defect which can reduce the carrying<br />
capacity of the structure ifno repair is carried out within<br />
the next 3-10 years. The damage must be repaired within<br />
3- 10 years.<br />
3C = Serious damage/defect which can rcduce the carrying<br />
capacity of the structure ifno repair is carried out within<br />
the next 1-3 years. The damage must bc repaired within<br />
\-3 years.<br />
4C = Critical damage which has reduced or is about to reduce<br />
the carrying capacity of the structure. The damage must<br />
be repaired immediately or within half a year if safety<br />
precautions shall be avoided. Report on the findings<br />
shall be submitted to the <strong>Bridge</strong> Engineer immedia<br />
tely.<br />
Damage influencing the<br />
Traffic Safety<br />
Damage inftuencing the<br />
Maintenance Cost<br />
lT ~<br />
2T ~<br />
3T ~<br />
4T ~<br />
lM ~<br />
Minor damage/defect that might in the long run present<br />
danger to the traffic safety. The damage m ight not requi<br />
re to be repaired within the coming 10 years.<br />
Average damage/defect which can reduce the traffic<br />
safety if no repair is carried out within the nex t 3-1 0<br />
years. The damage must be repaired withill 3- 10 years.<br />
Serious damage/defect whi ch can reduce t he traffic safe<br />
ty lfno repair is carried out within the nex t 1-3 years.<br />
The damage must be repai red within 1-3 years.<br />
Critical damage which has reduced or is about to reduce<br />
traffic safety. The damage must be repaired immediately<br />
or wi thin half a year if safety precautions s hall be avo<br />
ided.<br />
Report on the findings shall be submitted to the<br />
<strong>Bridge</strong> Engineer immediately.<br />
Minor damage/defect that in the long run, is considered<br />
to influence the maintenance costs. The damage mi gh t<br />
not require to be repaired with in the coming 10 years.