Development <strong>of</strong> Atchchuvali Industrial Estate,<br />

Jaffna, Sri Lanka.<br />

Page PP/14<br />

Pricing Preambles<br />

xxv. All other incidental works and necessary works which are not described in the BOQ, but<br />

described in the aforesaid specifications and or shown in the drawings for the proper completion<br />

<strong>of</strong> the relevant items <strong>of</strong> work;<br />

xxvi. Establishment charges, overheads and pr<strong>of</strong>it.<br />

xxvii. All necessary scaffolding work including supply, erection and dismantling.<br />

Measurement Methods<br />

The final quantities shall be computed net using dimensions from the drawings, relative to Existing Ground<br />

Levels as per the agreed drawings persuading to the Conditions <strong>of</strong> Contract, except where clearly stated<br />

otherwise under individual items in the drawings and the BOQ. No allowance shall be made for bulking,<br />

shrinkage or waste.<br />

If geometric tolerances on the Contractor’s work, whether they are within or without the specified<br />

tolerances, cause any increase in quantities relative to the computed net quantities from the drawings then<br />

such increases shall deem to be included in the rates and such additional quantities shall not be included<br />

in the measurement for payment. No deduction shall be made for tolerances within the specified limits.<br />

Quantities shall be measured with the same place <strong>of</strong> decimal as stated in the bills.<br />

3.2 EXCAVATION AND EARTH WORK<br />

1. All work under this section is measured net.<br />

2. The Contractor shall be responsible for the design and execution <strong>of</strong> the excavation and earthwork<br />

support methods where necessary, which is subject to scrutiny by the Engineer. However, scrutiny<br />

by the Engineer shall not in any way relieve the Contractor <strong>of</strong> his responsibilities and duty regarding<br />

care <strong>of</strong> work.<br />

3. Existing Ground level indicated in the drawings shall be the level <strong>of</strong> trimmed ground free <strong>of</strong> all<br />

structure, paving, plinths, foundations and the like.<br />

4. Depths <strong>of</strong> all excavations are taken from the immediate filled ground level.<br />

5. Where a compacted earth fill is specified or indicated in drawings it shall mean approved granular fill<br />

<strong>of</strong> imported material, or selected excavated material.<br />

6. Dewatering shall mean disposal <strong>of</strong> surface water and ground water collected or found in excavated<br />

areas which is likely to adversely affect the Works.<br />

7. Disposal <strong>of</strong> ground or surface water shall be done by any accepted method, with the least<br />

inconvenience to the public and in accordance with relevant local government regulations.<br />

8. Excess excavated material shall be the property <strong>of</strong> the Contractor, who is responsible for disposal <strong>of</strong><br />

such material at a location <strong>of</strong>f or within the site as quickly as possible, as directed by the Engineer.