Development <strong>of</strong> Atchchuvali Industrial Estate,<br />

Jaffna, Sri Lanka.<br />

Page PP/11<br />

Pricing Preambles<br />

The inserted rates for labour shall cover all bonuses, statutory charges and all other charges and costs in<br />

respect <strong>of</strong> or incidental to the employment <strong>of</strong> the said labour, except only the cost <strong>of</strong> materials and<br />

Constructional Plat. The rate shall also include the costs in respect <strong>of</strong> portable tools such as picks,<br />

shovels, barrows, trowels, ladders, hand-saws, buckets, trestles, hammers, chisels and all items <strong>of</strong> a like<br />

nature, which for the purpose <strong>of</strong> work executed on a day-work basis shall not be considered as<br />

Constructional Plant.<br />

(ii)<br />

Materials and Goods<br />

Payment in respect <strong>of</strong> materials or goods used in the execution <strong>of</strong> work on a day-work basis shall be net<br />

cost <strong>of</strong> materials or goods plus the required percentage addition stated in the Appendix to tender.<br />

The “net cost <strong>of</strong> materials” means the net cost <strong>of</strong> such materials or goods delivered by the supplier to store<br />

or stockpile on the Site.<br />

The stated rate shall cover the costs <strong>of</strong> taking delivery and putting into the store or stockpile, usage <strong>of</strong> any<br />

minor tools/equipment not listed under plant and equipment, storage, overheads and all other charges and<br />

costs in respect <strong>of</strong> or incidental to the procurements and handling <strong>of</strong> such materials or goods.<br />

The costs <strong>of</strong> taking the materials from the store or stock pile on site to the place where they are used shall<br />

be paid for at the appropriate day-work rates for labour and Constructional Plant.<br />

(iii)<br />

Constructional Plant<br />

The inserted rate for Constructional Plant shall be paid for the plant when actually employed directly in the<br />

execution <strong>of</strong> the work on a day-work basis, excluding any travelling time, associated movement on the site<br />

with a prime mover or idling hours. The rate shall include the following:<br />

a) The cost <strong>of</strong> Constructional Plant including maintenance and spares, fuel and fuel distribution,<br />

oil grease, and any other consumables.<br />

b) The cost <strong>of</strong> crews, operators/drivers and attendants.<br />

c) All overheads, pr<strong>of</strong>its and other costs associated with the plant being required to work on a<br />

day-work basis.