15.11.2014 Views

Download Tender Document - High Commission of India, Colombo

Download Tender Document - High Commission of India, Colombo

Download Tender Document - High Commission of India, Colombo

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

MEASURED PRICE CONSTRUCTION CONTRACT<br />

General Conditions<br />

Operational excellence for results that matter<br />

to give such notice within 14 days <strong>of</strong> such conditions being encountered.<br />

(f)<br />

(g)<br />

The notice given under Sub-Clause 4.12(d) shall describe the physical<br />

conditions in sufficient detail as required by the Employer's Representative<br />

and so that those conditions can be inspected by the Employer's<br />

Representative and shall set out the reasons why the Contractor considers<br />

them to be Unforeseeable. The Contractor shall continue executing the<br />

Works, using all reasonable measures as are appropriate for the physical<br />

conditions, and shall comply with any reasonable instructions the Employer's<br />

Representative may give.<br />

If and to the extent that the Contractor encounters physical conditions which<br />

the Employer' Representative determines are Unforeseeable, gives a Claim<br />

Notice in accordance with Sub-Clause 4.12(d), and suffers delay and/or<br />

incurs Costs due to these conditions, the Contractor shall be entitled subject<br />

to Sub-Clause 20.1 [Contractor's Claims] to:<br />

(i)<br />

(ii)<br />

an extension <strong>of</strong> time for any such delay, if completion is or will be<br />

delayed under Sub-Clause 8.4 [Extension <strong>of</strong> Time for Completion];<br />

and<br />

payment <strong>of</strong> any such Costs, which shall be added to the Contract<br />

Price as a Variation.<br />

(h)<br />

After receiving the Claim Notice under Sub-Clause 4.12(g) and inspecting<br />

and/or investigating these physical conditions, the Employer's Representative<br />

shall proceed in accordance with Sub-Clause 20.1 [Contractor's Claims] and<br />

Sub-Clause 3.5 [Determinations] to agree or determine:<br />

(i)<br />

(ii)<br />

whether and (if so) to what extent these physical conditions were<br />

Unforeseeable; and<br />

the matters described in Sub-Clauses 4.12(g)(i) and (ii) related to this<br />

extent.<br />

(i)<br />

(j)<br />

Before an extension <strong>of</strong> time for any such delay, or additional Costs is finally<br />

agreed or determined under Sub-Clause 4.12(h), the Employer's<br />

Representative may also review whether other physical conditions in similar<br />

parts <strong>of</strong> the Works (if any) were more favourable than could reasonably have<br />

been foreseen at the Date <strong>of</strong> the Contract. If and to the extent that these<br />

more favourable conditions were encountered, the Employer's<br />

Representative may proceed in accordance with Sub-Clause 3.5<br />

[Determinations] to determine the reductions in Costs and a reduction in any<br />

entitlement to an extension <strong>of</strong> time, which were due to these conditions,<br />

which may be included (as deductions) in the Contract Price and Payment<br />

Certificates. The net effect <strong>of</strong> all adjustments under Sub-Clause 4.12(g)(ii)<br />

and all these reductions, for all the physical conditions encountered in similar<br />

parts <strong>of</strong> the Works, shall not result in a net reduction in the Contract Price or<br />

Time for Completion.<br />

The Employer's Representative may take account <strong>of</strong> any evidence <strong>of</strong> the<br />

physical conditions foreseen by the Contractor prior to the Date <strong>of</strong> the<br />

© UNOPS 2011 40

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!