MEASURED PRICE CONSTRUCTION CONTRACT<br />

General Conditions<br />

Operational excellence for results that matter<br />

9.3 Retesting<br />

Retesting<br />

If the Works, or a Section, fail to pass the Tests on Completion, Sub-Clause 7.5<br />

[Rejection] shall apply, and the Employer's Representative or the Contractor may<br />

require the failed Tests on Completion, and Tests on Completion on any related<br />

work, to be repeated under the same terms and conditions.<br />

9.4 Failure to Pass Tests on Completion<br />

Failure to Pass Tests on Completion<br />

(a)<br />

If the Works, or a Section, fail to pass the Tests on Completion repeated<br />

under Sub-Clause 9.3 [Retesting], the Employer's Representative may, in its<br />

sole and absolute discretion:<br />

(i) order further repetition <strong>of</strong> Tests on Completion under Sub-Clause 9.3<br />

[Retesting];<br />

(ii)<br />

(iii)<br />

if the failure deprives the Employer <strong>of</strong> substantially the whole benefit<br />

<strong>of</strong> the Works or Section, reject the Works or Section (as the case may<br />

be), in which event the Employer shall have the same remedies as<br />

are provided in Sub-Clause 11.4(b) [Failure to Remedy Defects]; or<br />

issue a Taking Over Certificate, if the Employer so requests.<br />

(b)<br />

(c)<br />

In the event <strong>of</strong> the application <strong>of</strong> Sub-Clause 9.4(a)(iii), the Contractor shall<br />

proceed in accordance with all <strong>of</strong> its other obligations under the Contract, and<br />

the Contract Price shall be reduced by such amount as shall be appropriate<br />

to cover the reduced value to the Employer as a result <strong>of</strong> this failure.<br />

Unless the relevant reduction for this failure is stated (or its method <strong>of</strong><br />

calculation is defined) in the Contract, the Employer may require the<br />

reduction to be:<br />

(i)<br />

(ii)<br />

agreed by both Parties (in full satisfaction <strong>of</strong> this failure only) and paid<br />

before this Taking Over Certificate is issued; or<br />

determined and paid under Sub-Clause 3.5 [Determinations].<br />

10. EMPLOYER'S TAKING OVER<br />

10.1 Taking Over <strong>of</strong> the Works and Sections<br />

Taking Over <strong>of</strong> the Works and Sections<br />

(a)<br />

Except as stated in Sub-Clause 9.4 [Failure to Pass Tests on Completion],<br />

the Works shall be Taken Over by the Employer when:<br />