STREET<br />
Annual Concrete Street Rehabilitation <strong>Program</strong><br />
COSTS ITEMIZED U nprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design -<br />
Acquisition -<br />
Construction 7,379.3 723.1 748.4 445.6 801.7 276.5 4,384.0<br />
TOTAL 7,379.3 - 723.1 748.4 445.6 801.7 276.5 4,384.0<br />
FUNDING SOURCES<br />
GOB 4,653.9 482.1 498.9 187.4 534.5 - 2,951.0<br />
Road Use 2,725.4 241.0 249.5 258.2 267.2 276.5 1,433.0<br />
-<br />
TOTAL 7,379.3 - 723.1 748.4 445.6 801.7 276.5 4,384.0<br />
AA<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
X A Existing Need: Plans and<br />
Approval Complete<br />
B<br />
C<br />
D<br />
E<br />
Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
3rd Party Approvals<br />
Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
PROJECT STATUS Completed In Year Future<br />
Studies/Need Asses. X<br />
Survey/Prel. Design X<br />
Acquisitions<br />
Assessment Schedule 10-14 X<br />
Plans<br />
State/Federal Approval<br />
Bid/Construction 10-14 X<br />
Other<br />
Description: Proposed is an annual street<br />
rehabilitation program to provide full depth<br />
concrete patching at locations identified in the<br />
2009 Pavement Management Report. The report<br />
serves as the foundation to identify annual and<br />
future street rehabilitation projects.<br />
Justification: This annual rehabilitation program<br />
will delay total reconstruction and decrease long<br />
term maintenance costs. The projects will<br />
supplement the Public Works activities to improve<br />
the pavement ratings set out in the Pavement<br />
Management Report.<br />
Project Status:. This will be an ongoing program<br />
that is bid out annually. The 2012 project is<br />
separately scheduled in this <strong>CIP</strong> as the “Douglas<br />
Avenue Preservation Project – 100 th Street to<br />
111 th Street”. The 2014 project is separately<br />
scheduled in this <strong>CIP</strong> as the “Aurora Avenue<br />
Preservation Project: 70 th Street to 86 th Street”.<br />
Effect on Operating Budget: The annual Road<br />
Use fund allocation in the operating budget will<br />
decrease significantly from prior years.<br />