STREET<br />
Aurora Avenue: 128 th Street to 142 nd Street<br />
COSTS ITEMIZED U nprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design 452.5 131.7 320.8<br />
Acquisition 150.0 150.0<br />
Construction 3,016.1 877.7 2,138.4<br />
TOTAL 3,618.6 - 1,009.4 - - - - 2,609.2<br />
FUNDING SOURCES<br />
GOB 2,870.7 # 837.5 2,033.2<br />
Spec Assmt 747.9 171.9 576.0<br />
-<br />
Sub-Total 3,618.6 - 1,009.4 - - - - 2,609.2<br />
Less Prior Debt Issued in 2009 (705.0)<br />
GOB remaining balance to issue 132.5<br />
Spec Assmt 171.9<br />
TOTAL 2,913.6 304.4 2,609.2<br />
AA<br />
A<br />
B<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
Existing Need: Plans and<br />
Approval Complete<br />
Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
X C Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
D<br />
E<br />
3rd Party Approvals<br />
Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
Description: Proposed is the paving <strong>of</strong> Aurora<br />
Avenue from 128 th Street to 142 nd Street.<br />
Justification: This project is a rural cross section<br />
road that is in need <strong>of</strong> reconstruction due to its<br />
traffic volume.<br />
Project Status: The project is in the development<br />
stage. Phase I – 2010: would pave a quarter mile<br />
along the frontage <strong>of</strong> the Webster Elementary School<br />
and Jeff Harm Park. Phase II – 2015+: would start<br />
one quarter mile west <strong>of</strong> 128 th Street and extend to<br />
142 nd Street in 2015+. Approximately one-half <strong>of</strong><br />
this Phase II is in the <strong>City</strong> <strong>of</strong> Grimes.<br />
Effect on Operating Budget: Minimal effect,<br />
estimated at $1,000 annually for maintenance.<br />
PROJECT STATUS<br />
Completed<br />
In Year<br />
Future<br />
Studies/Need Asses. 07<br />
Survey/ Prel. Design 09<br />
Acquisition 09<br />
Assessment Schedule 10<br />
Plans 09<br />
State/Federal Approval<br />
Bid/Construction 10 X<br />
Other<br />