STREET<br />
86 th Street and Northpark Drive: Turn Lanes<br />
COSTS ITEMIZED Unprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design 110.1 110.1<br />
Acquisition 50.0 50.0<br />
Construction 684.7 684.7<br />
TOTAL 844.8 - 844.8 - - - - -<br />
FUNDING SOURCES<br />
TIF 453.8 @ 453.8<br />
Johnston 391.0 391.0<br />
-<br />
Sub-Total 844.8 - 844.8 - - - - -<br />
Less Prior Debt Issued - (453.8) - - - - -<br />
TOTAL 391.0 - 391.0 - - - - -<br />
@ the TIF was issued in 2008, project construction delayed from 2009 to 2010.<br />
AA<br />
A<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
Existing Need: Plans and<br />
Approval Complete<br />
X B Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
C<br />
D<br />
Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
3rd Party Approvals<br />
Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
Description: Proposed is the construction <strong>of</strong><br />
dual left turn lanes for north and south bound<br />
86 th Street at Northpark Drive.<br />
Justification: Adding dual left turn lanes would<br />
increase the capacity <strong>of</strong> the intersection and<br />
reduce travel time through the intersection.<br />
Project Status: The project is in the<br />
development stage.<br />
Effect on Operating Budget: Slightly increase<br />
the amount <strong>of</strong> paving to maintain.<br />
E<br />
Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
PROJECT STATUS<br />
Completed<br />
In Year<br />
Studies/Need Asses. 08<br />
Survey/ Prel. Design 08<br />
Acquisition<br />
Assessment Schedule<br />
Plans 08<br />
State/Federal Approval<br />
Bid/Construction 10<br />
Other<br />
Future<br />
98