STREET<br />
100 th Street Extension<br />
COSTS ITEMIZED U nprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design 263.4 100.0 163.4<br />
Acquisition -<br />
Construction 2,036.6 2,036.6<br />
TOTAL 2,300.0 - - - - 100.0 2,200.0 -<br />
FUNDING SOURCES<br />
TIF 918.0 100.0 818.0<br />
Private-Developer 462.0 462.0<br />
STP 920.0 920.0<br />
TOTAL 2,300.0 - - - - 100.0 2,200.0 -<br />
AA<br />
A<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
Existing Need: Plans and<br />
Approval Complete<br />
X B Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
C<br />
D<br />
Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
3rd Party Approvals<br />
Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
E Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
X ART<br />
PROJECT STATUS<br />
Completed<br />
In Year<br />
Studies/Need Asses.<br />
Survey/ Prel. Design 12<br />
Acquisition<br />
Assessment Schedule 13<br />
Plans 13<br />
State/Federal Approval<br />
Bid/Construction 14<br />
Other<br />
Future<br />
Description: Proposed is the construction <strong>of</strong><br />
100 th Street from the Interstate 35/80 Bridge to<br />
N.W. 54 th Avenue. This project would provide<br />
for the expansion <strong>of</strong> 100 th Street from just north<br />
<strong>of</strong> Interstate 35/80 to just south <strong>of</strong> 54 th Avenue,<br />
from a rural cross section 2 lane roadway to an<br />
urban 4 lane roadway. Grading and storm sewer<br />
are included in the project.<br />
Justification: As the volume <strong>of</strong> traffic increases<br />
on 100 th Street, the existing temporary asphalt<br />
paving will deteriorate. 100 th Street provides<br />
access to Northpark Drive and Plum Drive<br />
which will have future retail and <strong>of</strong>fice park<br />
developments, and 100 th Street also provides<br />
access from <strong>Urbandale</strong> to Grimes and Johnston.<br />
Project Status: Plans are in the conceptual<br />
stage. 100 th Street will be constructed with two<br />
through lanes in each direction, with left turn<br />
lanes. In Fall, 2009, the <strong>City</strong> applied for STP<br />
funding for 40% <strong>of</strong> the project cost.<br />
Effect on Operating Budget: Decrease in<br />
maintenance costs due to the elimination <strong>of</strong> the<br />
asphalt surface.<br />
99