STREET<br />

Northpark Drive Extension: 100 th Street<br />

COSTS ITEMIZED U nprogrammed<br />

(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />

Design 243.0 243.0<br />

Acquisition -<br />

Construction 1,620.0 1,620.0<br />

TOTAL 1,863.0 - - - - - - 1,863.0<br />

FUNDING SOURCES<br />

TIF 1,342.2 1,342.2<br />

Spec Assmt 520.8 520.8<br />

-<br />

TOTAL 1,863.0 - - - - - - 1,863.0<br />

AA<br />

A<br />

B<br />

C<br />

PROJECT CLASSIFICATION<br />

Imminent Need or Emergency:<br />

Special Opportunity<br />

Existing Need: Plans and<br />

Approval Complete<br />

Existing or Developing Need:<br />

Minor Plan Approvals Needed<br />

Plans Under Preparation: Need<br />

Acquistion, Assessment, or<br />

3rd Party Approvals<br />

X D Growing Demand: No plans,<br />

need further study or lengthy<br />

approval process<br />

E<br />

Future need as growth<br />

continues; other projects<br />

completed, or funding obtained<br />

PROJECT STATUS<br />

Completed<br />

In Year<br />

Future<br />

Studies/Need Asses.<br />

X<br />

Survey/ Prel. Design 07 X<br />

Acquisition 07<br />

Assessment Schedule<br />

X<br />

Plans 07 X<br />

State/Federal Approval<br />

Bid/Construction<br />

X<br />

Other<br />

Description: This project would extend Northpark<br />

Drive as a three-lane roadway to the west <strong>of</strong> 100 th<br />

Street and provide a connection to NW 54 th<br />

Avenue, which is a common roadway with the <strong>City</strong><br />

<strong>of</strong> Grimes. This extension would provide a vital<br />

east to west link for this business park area north <strong>of</strong><br />

Interstate 35/80.<br />

Justification: The connection to 100 th Street is<br />

important for the development <strong>of</strong> this area as a<br />

successful business park. Initial traffic studies<br />

show that the intersection <strong>of</strong> 86 th Street and<br />

Northpark Drive cannot function as the only access<br />

point.<br />

Project Status: The proposed phase would<br />

construct a 43-foot wide, three-lane roadway--one<br />

through lane in each direction, plus a left turn lane.<br />

Effect on Operating Budget: Increase<br />

approximately $500 annually.<br />