STREET<br />
Douglas Parkway: 156 th Street to West Corporate<br />
Limit<br />
COSTS ITEMIZED U nprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design 233.4 233.4<br />
Acquisition 150.0 150.0<br />
Construction 1,556.1 1,556.1<br />
TOTAL 1,939.5 - 1,939.5 - - - - -<br />
FUNDING SOURCES<br />
GOB 1,633.5 1,633.5<br />
Spc Assmt 306.0 306.0<br />
-<br />
TOTAL 1,939.5 - 1,939.5 - - - - -<br />
AA<br />
A<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
Existing Need: Plans and<br />
Approval Complete<br />
X B Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
X<br />
C<br />
D<br />
E<br />
Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
3rd Party Approvals<br />
Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
ART<br />
PROJECT STATUS<br />
Completed<br />
In Year<br />
Studies/Need Asses. 09<br />
Survey/ Prel. Design 09<br />
Acquisition 09<br />
Assessment Schedule 09<br />
Plans 09<br />
State/Federal Approval<br />
Bid/Construction 10<br />
Other<br />
Future<br />
Description: Proposed is the construction <strong>of</strong><br />
Douglas Parkway from 156 th Street to the west<br />
corporate line as a four-lane boulevard. This<br />
project is being planned with the <strong>City</strong> <strong>of</strong> Clive<br />
and the Waukee School District. The Waukee<br />
School District plans to open a new elementary<br />
school on the south side <strong>of</strong> Douglas Parkway,<br />
west <strong>of</strong> the <strong>Urbandale</strong>/Clive boundary in 2010.<br />
The street construction is being planned to open<br />
with the school. Additional improvements would<br />
include grading and storm sewers. The roadway<br />
alignment would follow the existing roadway’s<br />
centerline, except at the locations where <strong>of</strong>fsets<br />
have been approved to the south.<br />
Justification: Douglas Parkway will be a major<br />
east/west arterial that connects the western areas<br />
<strong>of</strong> <strong>Urbandale</strong> with the rest <strong>of</strong> the community.<br />
Part <strong>of</strong> the cost for this project would be assessed<br />
to the adjacent property owners.<br />
Project Status: This future project is in the<br />
development stage and preliminary plans are not<br />
completed.<br />
Effect on Operating Budget: Decrease in<br />
maintenance costs due to the elimination <strong>of</strong> the<br />
asphalt surface and the ditches.<br />
Hazard Mitigation Project: Tentatively<br />
designated by <strong>City</strong> staff as an eligible project.<br />
81