PARKS<br />
Trail: Oakwood Park Trail (Sutton Drive)<br />
COSTS ITEMIZED Unprogrammed<br />
(In 000's) TOTALS 2010 2011 2012 2013 2014 2015+<br />
Design -<br />
Acquisition -<br />
Construction 115.6 115.6<br />
TOTAL 115.6 - - - - - - 115.6<br />
FUNDING SOURCES<br />
GOB 115.6 115.6<br />
-<br />
-<br />
TOTAL 115.6 - - - - - - 115.6<br />
AA<br />
A<br />
B<br />
C<br />
PROJECT CLASSIFICATION<br />
Imminent Need or Emergency:<br />
Special Opportunity<br />
Existing Need: Plans and<br />
Approval Complete<br />
Existing or Developing Need:<br />
Minor Plan Approvals Needed<br />
Plans Under Preparation: Need<br />
Acquistion, Assessment, or<br />
3rd Party Approvals<br />
X D Growing Demand: No plans,<br />
need further study or lengthy<br />
approval process<br />
Description: Proposed is the construction <strong>of</strong> an<br />
asphalt bike trail and the installation <strong>of</strong> a bridge<br />
through the Oakwood open space, from Oakwood<br />
Drive to Sutton Drive and 63 rd Street. The trail<br />
would be 8 feet wide.<br />
Justification: The trail would connect to existing<br />
trails in the neighborhood.<br />
Project Status: Future need. A plan and design<br />
will be needed.<br />
Effect on Operating Budget: Minimal expense<br />
to maintain trail.<br />
E<br />
Future need as growth<br />
continues; other projects<br />
completed, or funding obtained<br />
PROJECT STATUS<br />
Completed<br />
In Year<br />
Future<br />
Studies/Need Asses.<br />
Survey/ Prel. Design<br />
X<br />
Acquisition<br />
Assessment Schedule<br />
Plans<br />
X<br />
State/Federal Approval<br />
Bid/Construction<br />
X<br />
Other<br />