80 API STANDARD 65-2<br />

Job Executi<strong>on</strong><br />

A well executed cement job is critical to isolating potential flow z<strong>on</strong>es.<br />

Circulati<strong>on</strong> and<br />

C<strong>on</strong>diti<strong>on</strong>ing<br />

Density C<strong>on</strong>trol<br />

Pre-flushes and<br />

Spacers<br />

Placement Rates<br />

Centralizers<br />

Special Blending<br />

Mixing<br />

Liquid Additive<br />

System<br />

Was the well circulated and the drilling fluid c<strong>on</strong>diti<strong>on</strong>ed prior to cementing<br />

Was the cement placed across potential flow z<strong>on</strong>es mixed within a density range or solid to liquid ratio<br />

range that did not compromise the slurry performance (static gel strength, thickening time, etc.) required for<br />

flow preventi<strong>on</strong><br />

Were spacers mixed and pumped as designed including rheology, density and volume<br />

Were the placement rates adequate for effective drilling fluid removal<br />

Were centralizers properly installed as designed<br />

If used, were specialty blended cements prepared, transported and stored in accordance with the suppliers<br />

established guidelines<br />

If used, was the liquid additive system calibrated before the cement job and was an inventory check<br />

performed after the job to verify actual usage<br />

Post Job M<strong>on</strong>itoring During WOC was the annulus m<strong>on</strong>itored and kept full<br />

Special Operati<strong>on</strong>al C<strong>on</strong>siderati<strong>on</strong>s<br />

Barrier Acceptance<br />

Diverter or BOP<br />

Obstructi<strong>on</strong><br />

Hydrostatic<br />

Overbalance<br />

Foamed Cement<br />

Foamer, Stabilizer<br />

and Nitrogen<br />

Injecti<strong>on</strong><br />

(foamed cement)<br />

Cement Plugs<br />

If the criteria for verificati<strong>on</strong> of a mechanical barrier or cement cannot be met the operator shall establish an<br />

appropriate course of acti<strong>on</strong> with the regulator or permitting authority.<br />

Operators or rig c<strong>on</strong>tractors shall not run tubing in the annulus between the casing and the diverter, or<br />

BOP, after completi<strong>on</strong> of the cementing operati<strong>on</strong> and prior to determining the well has no potential for flow.<br />

<str<strong>on</strong>g>The</str<strong>on</strong>g> operator shall perform hydrostatic pressure calculati<strong>on</strong>s to verify sufficient hydrostatic overbalance<br />

pressure throughout the well prior to washing out to the mudline suspensi<strong>on</strong> hanger.<br />

Operators and cementing service providers shall perform a risk assessment prior to utilizing foamed<br />

cement to isolate a potential flow z<strong>on</strong>e.<br />

<str<strong>on</strong>g>The</str<strong>on</strong>g> results of this assessment shall be incorporated into the cementing plan.<br />

Will the foamer, stabilizer and nitrogen injecti<strong>on</strong> be c<strong>on</strong>trolled by an automated process system Were the<br />

foamer, stabilizer and nitrogen ratios within design tolerances<br />

Cement plugs shall be installed and verified as required by regulati<strong>on</strong>s.