Performance Results<br />

63<br />

Major investment projects<br />

In 2014, gas production capex was RUB 182.3bn; oil and gas condensate production capex was<br />

RUB 173.4bn.<br />

Major production capex was made to develop Cenomanian-Aptian layers of the Bovanenkosvoye<br />

OGCF, and to implement the Comprehensive Programme for Upgrading and Technical<br />

Re-equipment of Gas Production Facilities.<br />

<strong>Gazprom</strong> Group’s capex in exploration and production of oil and gas condensate targeted<br />

construction of facilities at the Novoportovskoye and Prirazlomnoye fields, development of the<br />

Priobskoye field, <strong>Gazprom</strong> neft’s fields in the Orenburg Region and in Iraq.<br />

Commissioned hydrocarbon production facilities in 2014<br />

— Gas Processing Unit 1 with the capacity of 30 bcm of gas per year at the Bovanenkovskoye OGCF;<br />

— 3 BCS with a total capacity of 219 MW at the Bovanenkovskoye OGCF (125 MW), Vyngayakhinskoye gas production<br />

site (64 MW), and the Urengoyskoye OGCF (30 MW);<br />

— 127 new gas production wells (including 95 wells at the Bovanenkovskoye field) and 828 new oil production wells<br />

Production drilling was 125.6 thousand m of gas wells and 2,948.5 thousand m of oil wells.<br />

Long-term financial investments in exploration and production of oil and gas condensate were<br />

driven by the increased share in OOO SeverEnergia and construction of facilities at the Messoyakhskoye<br />

group of fields.<br />