72<br />
Performance Results<br />
<strong>Gazprom</strong>, on a parity basis with OAO SIBUR Holding, bought a 50% interest in OOO Poliom,<br />
a joint venture operating the facilities of the Omsk Polypropylene Plant. <strong>Gazprom</strong> neft is to supply<br />
to OOO Poliom raw materials (propane-propylene fraction from the Omsk Refinery), and<br />
OAO SIBUR Holding is to sell the products made by the joint venture through its distribution chain.<br />
Oil refining, petrochemistry and mineral fertiliser production at <strong>Gazprom</strong> neftekhim Salavat<br />
facilities<br />
In 2014, the production facilities of <strong>Gazprom</strong> neftekhim Salavat refined 8.3 mm tonnes of oil and<br />
gas condensate (5.5 mm tonnes of oil and 2.8 mm tonnes of gas condensate) at a 79% processing<br />
depth.<br />
The reduction of gasoline output was caused by unscheduled shutdowns of conversion units<br />
and longer repair time. The production output of HDPE, polystyrene, ethylene and urea was increased.<br />
In 2014, refineries started producing SMT-1 (MDO) low-viscosity marine fuel in accordance<br />
with high environmental standards. Also, a declaration of conformity was obtained for Euro 5 regular<br />
diesel fuel production facilities.<br />
Major investment projects<br />
<strong>Gazprom</strong> Group’s refining capex increased by 23.5% (RUB 25.7bn) y-o-y to reach RUB 135.1bn.<br />
Commissioning of hydrocarbons processing and gas and petrochemistry production facilities<br />
— Orenburg Helium Plant commissioned an OG-500 helium liquefying unit of 4.2 mm litres per year.<br />
— Surgut CSP commissioned a condensate stabilisation unit (process lines 8 and 9) of 4 mm tonnes per year.<br />
— Astrakhan GPP commissioned an isomerisation unit of 300 thousand tonnes per year.<br />
— <strong>Gazprom</strong> neft’s refineries completed several major upgrades. The Omsk Refinery commissioned a terminal<br />
fordraining, storing and injecting gas condensate for processing to increase light oil product output. The<br />
Moscow Refinery upgraded the AVT-6 primary oil refining unit and commissioned a sulphur granulation unit.<br />
OAO Slavneft-YANOS completed an upgrade of several units used in the production of motor gasoline: catalytic<br />
cracking, sulphuric acid alkylation, and methyl tertiary butyl ether units.<br />
The bulk of the capital expenditures for refining was allocated for the following projects: construction<br />
of the Novy Urengoy Gas Chemical Complex, upgrading <strong>Gazprom</strong> neft Group refinery<br />
capacities, modernisation at the Astrakhan Gas Processing Plant, construction of the Urengoy<br />
— Surgut gas condensate pipeline (second line), and construction and upgrade of oil refining<br />
and petrochemical facilities at <strong>Gazprom</strong> neftekhim Salavat.<br />
OAO <strong>Gazprom</strong> Annual Report 2014