10.12.2012 Views

Low Impact Development Manual for Michigan - OSEH - University ...

Low Impact Development Manual for Michigan - OSEH - University ...

Low Impact Development Manual for Michigan - OSEH - University ...

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

The construction cost of constructed wetlands varies<br />

greatly depending on the configuration, location, site<br />

specific conditions, etc. Typical construction costs<br />

in 2004 dollars range from approximately $30,000 to<br />

$65,000 per acre (USEPA Wetlands Fact Sheet, 1999).<br />

Costs are generally most dependent on the amount of<br />

earthwork and planting. Annual maintenance costs have<br />

been reported to be approximately two to five percent of<br />

the capital costs (USEPA, 2000).<br />

The construction cost of underground detention can<br />

vary greatly depending on the design, configuration,<br />

location, storage volume and media, and site specific<br />

conditions, among other factors. Typical construction<br />

costs are approximately $8 to $10 per cubic foot <strong>for</strong><br />

proprietary high capacity storage systems. Systems<br />

using uni<strong>for</strong>mly graded aggregate as the primary storage<br />

media will typically be less expensive but require<br />

additional area and/or depth <strong>for</strong> an equivalent storage<br />

volume.<br />

Annual maintenance costs <strong>for</strong> dry ponds and wet ponds<br />

have been reported to be approximately three to five<br />

percent of the capital costs, though there is little data<br />

available to support this. Alternatively, a community<br />

can estimate the cost of the maintenance activities<br />

outlined in the maintenance section. Ponds are longlived<br />

facilities (typically longer than 20 years). Thus,<br />

the initial investment into pond systems may be spread<br />

over a relatively long time period.<br />

General Specifications<br />

The following specifications are provided <strong>for</strong> in<strong>for</strong>mation<br />

purposes only. These specifications include<br />

in<strong>for</strong>mation on acceptable materials <strong>for</strong> typical applications,<br />

but are by no means exclusive or limiting. The<br />

designer is responsible <strong>for</strong> developing detailed specifications<br />

<strong>for</strong> individual design projects in accordance<br />

with the project conditions.<br />

Dry detention and underground<br />

structures<br />

Site preparation<br />

All excavation areas, embankments, and structure locations<br />

should be cleared and grubbed as necessary, but<br />

trees and existing vegetation should be retained and<br />

incorporated within the dry detention basin area where<br />

possible. Trees should not be removed unless absolutely<br />

necessary.<br />

Where feasible, trees and other native vegetation should<br />

be protected, even in areas where temporary inundation<br />

is expected. A minimum 10-foot radius around the inlet<br />

and outlet structures can be cleared to allow room <strong>for</strong><br />

construction.<br />

Any cleared material should be used as mulch <strong>for</strong><br />

erosion control or soil stabilization.<br />

Care should be taken to prevent compaction of the<br />

bottom of the reservoir. If compaction should occur,<br />

soils should be restored and amended.<br />

Earth fill material & placement<br />

• The fill material should be taken from approved<br />

designated excavation areas. It should be free<br />

of roots, stumps, wood, rubbish, stones greater<br />

than six inches, or other objectionable materials.<br />

Materials on the outer surface of the embankment<br />

must have the capability to support vegetation.<br />

• Areas where fill is to be placed should be<br />

scarified prior to placement. Fill materials <strong>for</strong> the<br />

embankment should be placed in maximum eightinch<br />

lifts. The principal spillway must be installed<br />

concurrently with fill placement and not excavated<br />

into the embankment.<br />

• Control movement of the hauling and spreading<br />

equipment over the site.<br />

Embankment core<br />

• The core should be parallel to the centerline of<br />

the embankment as shown on the plans. The top<br />

width of the core should be at least four feet. The<br />

height should extend up to at least the 10-year<br />

water elevation or as shown on the plans. The side<br />

slopes should be 1:1 or flatter. The core should be<br />

compacted with construction equipment, rollers,<br />

or hand tampers to assure maximum density<br />

and minimum permeability. The core should be<br />

placed concurrently with the outer shell of the<br />

embankment.<br />

• Construction of the berm should follow<br />

specifications by the project’s geotechnical<br />

engineer.<br />

Structure backfill<br />

• Backfill adjacent to pipes and structures should be<br />

of the type and quality con<strong>for</strong>ming to that specified<br />

<strong>for</strong> the adjoining fill material. The fill should be<br />

placed in horizontal layers not to exceed eight<br />

inches in thickness and compacted by hand tampers<br />

or other manually directed compaction equipment.<br />

The material should fill completely all spaces under<br />

and adjacent to the pipe. At no time during the<br />

LID <strong>Manual</strong> <strong>for</strong> <strong>Michigan</strong> – Chapter 7 Page 185

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!