10.12.2012 Views

Low Impact Development Manual for Michigan - OSEH - University ...

Low Impact Development Manual for Michigan - OSEH - University ...

Low Impact Development Manual for Michigan - OSEH - University ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Subsurface infiltration bed<br />

Source: Driesenga & Associates, Inc.<br />

• Per<strong>for</strong>ated pipes along the bottom of the bed<br />

can be used to evenly distribute runoff over the<br />

entire bed bottom. Continuously per<strong>for</strong>ated pipes<br />

should connect structures (such as cleanouts and<br />

inlet boxes). Pipes should lay flat along the bed<br />

bottom to provide <strong>for</strong> uni<strong>for</strong>m distribution of<br />

water. Depending on size, these pipes may provide<br />

additional storage volume.<br />

• Cleanouts or inlets should be installed at a few<br />

locations within the bed at appropriate intervals to<br />

allow access to the per<strong>for</strong>ated piping network and<br />

storage media.<br />

• Grading of adjacent contributing areas should<br />

be mildly sloped between one percent and three<br />

percent to facilitate drainage.<br />

• In areas with poorly-draining soils, subsurface<br />

infiltration areas may be designed to slowly<br />

discharge to adjacent wetlands or bioretention<br />

areas.<br />

• The subsurface bed and overflow may be designed<br />

and evaluated in the same manner as a detention<br />

basin to demonstrate the mitigation of peak flow<br />

rates. In this manner, detention basins may be<br />

eliminated or significantly reduced in size.<br />

• During construction, the excavated bed may serve<br />

as a temporary sediment basin or trap, which can<br />

reduce overall site disturbance. The bed should be<br />

excavated to at least one foot above the final bed<br />

bottom elevation <strong>for</strong> use as a temporary sediment<br />

trap or basin. Following construction and site<br />

stabilization, sediment should be removed and final<br />

grades established.<br />

Incorporating a Safety<br />

Factor into Infiltration<br />

BMP Design<br />

For the purposes of site suitability, areas with tested<br />

soil infiltration rates as low as 0.1 inches per hour may<br />

be used <strong>for</strong> infiltration BMPs. However, in the design<br />

of these BMPs and the sizing of the BMP, the designer<br />

should incorporate a safety factor. Safety factors between<br />

1 (no adjustment) and 10 have been used in the<br />

design of stormwater infiltration systems, with a factor<br />

of two being used in most cases. There<strong>for</strong>e a measured<br />

infiltration rate of 0.5 inches per hour should generally<br />

be considered as a rate of 0.25 inches per hour in<br />

design. See the Soil Infiltration Testing Protocol in Appendix<br />

E <strong>for</strong> guidance on per<strong>for</strong>ming infiltration tests.<br />

Modeling Infiltration<br />

Systems<br />

As discussed in Chapter 9 of this manual, infiltration<br />

systems can be modeled similarly to traditional detention<br />

basins. The marked difference with modeling<br />

infiltration systems is the inclusion of the infiltration<br />

rate, which can be considered as another outlet. For<br />

modeling purposes, it is sometimes useful to develop<br />

infiltration rates that vary (based on the infiltration<br />

area provided as the system fills with runoff) <strong>for</strong> inclusion<br />

in the stage-storage-discharge table.<br />

LID <strong>Manual</strong> <strong>for</strong> <strong>Michigan</strong> – Chapter 7 Page 208

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!