A Study of Lean Construction Practices in Gaza Strip
A Study of Lean Construction Practices in Gaza Strip
A Study of Lean Construction Practices in Gaza Strip
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
for measur<strong>in</strong>g the percent plan complete (PPC) and look for the causes <strong>of</strong> failure. In<br />
addition, PPC also helps to reduce the variation.<br />
2.5.4 Cycle time reduction<br />
The cycle time is the time required for execut<strong>in</strong>g the process traverse the construction<br />
flow. The cycle time is used to measure the flow processes and it is a more useful than<br />
cost and quality. It can be represented as follows:<br />
Cycle time = Process<strong>in</strong>g time + <strong>in</strong>spection time + wait time + move time<br />
The new construction philosophy aims to compress the cycle time, which forces the<br />
reduction <strong>of</strong> <strong>in</strong>spection, move and wait time.<br />
In addition to the forced elim<strong>in</strong>ation <strong>of</strong> wastes, compression <strong>of</strong> the total cycle time gives<br />
the follow<strong>in</strong>g benefits: faster delivery to the customer, reduced need to make forecasts<br />
about future demands, decrease <strong>of</strong> disruption <strong>of</strong> the construction process due to change<br />
orders, easier management because there are fewer customer orders to keep track <strong>of</strong>.<br />
The pr<strong>in</strong>ciple <strong>of</strong> cycle time compression also has other <strong>in</strong>terest<strong>in</strong>g implications:<br />
1. From the perspective <strong>of</strong> control, it is important that the cycles <strong>of</strong> deviation detection<br />
and correction be speedy.<br />
2. In design and plann<strong>in</strong>g, there are many open-ended tasks that benefit from an<br />
iterative search for successively better (if not optimal) solutions. The shorter the<br />
cycle time, the more cycles are affordable.<br />
3. From the po<strong>in</strong>t <strong>of</strong> view <strong>of</strong> improvement, every layer <strong>in</strong> an organizational hierarchy<br />
adds to the cycle time <strong>of</strong> error correction and problem solv<strong>in</strong>g. This simple fact<br />
provides the new construction philosophy’s motivation to decrease organizational<br />
layers, thereby empower<strong>in</strong>g the persons work<strong>in</strong>g directly with<strong>in</strong> the flow.<br />
Practical approaches to cycle time reduction <strong>in</strong>clude the follow<strong>in</strong>g: Elim<strong>in</strong>at<strong>in</strong>g work<strong>in</strong>-progress<br />
(this orig<strong>in</strong>al JIT goal reduces the wait<strong>in</strong>g time and thus the cycle time),<br />
reduc<strong>in</strong>g stor<strong>in</strong>g time and sett<strong>in</strong>g temporary stores so that mov<strong>in</strong>g distances are<br />
m<strong>in</strong>imized, thus keep<strong>in</strong>g th<strong>in</strong>gs mov<strong>in</strong>g; smooth<strong>in</strong>g and synchroniz<strong>in</strong>g the flows,<br />
reduc<strong>in</strong>g variability, chang<strong>in</strong>g activities from sequential order to parallel order, and<br />
eventually isolat<strong>in</strong>g the ma<strong>in</strong> value-added sequence from support work. In general,<br />
solv<strong>in</strong>g the control problems and constra<strong>in</strong>ts prevents a speedy flow.<br />
10