<strong>in</strong>ventory (Wrong storage <strong>of</strong> materials. Inadequate stack<strong>in</strong>g and <strong>in</strong>sufficient storage on<br />

site, <strong>in</strong>sufficient <strong>in</strong>structions about storage and stack<strong>in</strong>g and <strong>in</strong>appropriate storage<br />

lead<strong>in</strong>g to damage or deterioration), transportation (damage dur<strong>in</strong>g transportation, use<br />

<strong>of</strong> <strong>in</strong>adequate tools and equipments, poor storage, far distance between place <strong>of</strong> work<strong>in</strong>g<br />

and storage and unpacked supply), wait<strong>in</strong>g (wait<strong>in</strong>g for design documents and draw<strong>in</strong>gs<br />

motion, rework that does not comply with draw<strong>in</strong>gs and specifications, rework due to<br />

workers’ mistakes, delays <strong>in</strong> pass<strong>in</strong>g <strong>of</strong> <strong>in</strong>formation to the contractor on products,<br />

wait<strong>in</strong>g for workers or materials or equipments to arrive, equipment frequently<br />

breakdown, delay <strong>in</strong> commencement <strong>of</strong> project, delay <strong>in</strong> perform<strong>in</strong>g <strong>in</strong>spection and<br />

test<strong>in</strong>g by the consultant eng<strong>in</strong>eer and suspension <strong>of</strong> work by the owner and change<br />

orders ), motion (poor schedule to procurement the materials, unnecessary material<br />

handl<strong>in</strong>g, tradesmen slow/<strong>in</strong>effective, far distance between place <strong>of</strong> work<strong>in</strong>g and<br />

storage, poor distribution <strong>of</strong> materials <strong>in</strong> site, lack <strong>of</strong> proper ma<strong>in</strong>ta<strong>in</strong>ed pathways, and<br />

difficulty <strong>in</strong> motion <strong>of</strong> worker <strong>in</strong> the site ) and over-process<strong>in</strong>g (conversion waste from<br />

cutt<strong>in</strong>g uneconomical shapes, us<strong>in</strong>g excessive quantities <strong>of</strong> materials more than the<br />

required, wrong handl<strong>in</strong>g <strong>of</strong> materials, <strong>in</strong>sufficient <strong>in</strong>structions about handl<strong>in</strong>g, lack <strong>of</strong><br />

workers or tradesmen or subcontractors’ skill, difficulty <strong>in</strong> performance and<br />

pr<strong>of</strong>essional work, <strong>in</strong>teraction between various specialists and us<strong>in</strong>g untra<strong>in</strong>ed labors).<br />

In this thesis, we shall work on achiev<strong>in</strong>g the largest number <strong>of</strong> lean construction<br />

criteria because the project which was studied was completed. Waste <strong>in</strong> the value added<br />

process and non-value added process will be elim<strong>in</strong>ated or reduced. These wastes are<br />

particularly found <strong>in</strong> the project that was studied. Standardization and five why were the<br />

chosen tools to apply and implement lean construction <strong>in</strong> the <strong>Gaza</strong> <strong>Strip</strong>.<br />