4.5.1 Mobilization and excavation<br />
Table (4.18) shows that mobilization and excavation duration is equal to 151.35 hours.<br />
Before apply<strong>in</strong>g lean tools, it was 240 hours, and the percentage <strong>of</strong> value added time<br />
was 63%, the actual percent value added duration was 39%, and value added steps after<br />
apply<strong>in</strong>g the five why tools is 33% (before apply<strong>in</strong>g lean tools was 14%). Step1 and 3<br />
are merged.<br />
No. Process<br />
1<br />
2<br />
Table 4.18 Waste elim<strong>in</strong>ation <strong>in</strong> mobilization<br />
Site clean<strong>in</strong>g, <strong>in</strong>cludes remov<strong>in</strong>g<br />
trees<br />
Demolish<strong>in</strong>g the exist<strong>in</strong>g wall<strong>in</strong>g<br />
fence, rooms and any obstructed<br />
item exist<strong>in</strong>g <strong>in</strong> the proposed area<br />
Step<br />
number<br />
1<br />
Step<br />
Value<br />
added<br />
steps<br />
0<br />
Duration<br />
<strong>of</strong> process<br />
(hours)<br />
48<br />
Duration<br />
Value<br />
added<br />
time<br />
(hours)<br />
3<br />
Excavation <strong>of</strong> the natural ground<br />
to the required levels<br />
2 1 95.29 95.29<br />
4 Laboratory 3 0 8.06 0<br />
Total 3 1 151.35 95.29<br />
Percentage <strong>of</strong> value added<br />
33% 63%<br />
4.5.2 Pla<strong>in</strong> concrete<br />
Table (4.19) shows that pla<strong>in</strong> concrete duration is equal to 41.09 hours. Before apply<strong>in</strong>g<br />
lean tools, it was 63 hours, and the percent <strong>of</strong> value added time 9%, the actual duration<br />
was 6%, and value added step percent is 33%. It was 20% before apply<strong>in</strong>g lean tools.<br />
No.<br />
Table 4.19 Waste elim<strong>in</strong>ation <strong>in</strong> pla<strong>in</strong> concrete<br />
Process<br />
1 formwork concrete for<br />
"A-B"<br />
2 Cast pla<strong>in</strong> concrete<br />
3 Remove form work<br />
Total<br />
Percentage <strong>of</strong> value added<br />
Step<br />
number<br />
Step<br />
Value<br />
added steps<br />
0<br />
1<br />
2 1<br />
3 0<br />
3 1<br />
33%<br />
59<br />
Duration<br />
<strong>of</strong> process<br />
(hours)<br />
34.83<br />
3.97<br />
5.037<br />
43.83<br />
Duration<br />
9%<br />
0<br />
Value<br />
added<br />
time<br />
(hours)<br />
0<br />
3.97<br />
0<br />
3.97