(3) Transverse Construction Joints<br />

FHWA TECHNICAL ADVISORY T 5050.14<br />

June 5, 1990<br />

(a) A construction joint is formed by placing a slotted<br />

headerboard across the <strong>pavement</strong> to allow the<br />

longitudinal steel to pass through the joint. The<br />

longitudinal steel through the construction joint is<br />

increased a minimum of one-third by placing 3-foot<br />

long shear bars of the same nominal size between every<br />

other pair of longitudinal bars. No longitudinal<br />

steel splice should fall within 3 feet of the stopping<br />

side nor closer than 8 feet from the starting side of<br />

a construction joint. Refer to paragraph 4b(l)(e) for<br />

recommended splicing patterns. If it becomes<br />

necessary to splice within the above limits, each<br />

splice should be reinforced with a 6-foot bar of equal<br />

size. Extra care is needed to ensure both concrete<br />

quality and consolidation at these joints. If more<br />

than 5 days elapse between concrete pours, the<br />

adjacent <strong>pavement</strong> temperature should be stabilized by<br />

placing insulation material on it for a distance of<br />

200 feet from the free end at least 72 hours prior to<br />

placing new concrete. This procedure should reduce<br />

potentially high tensile stresses in the longitudinal<br />

steel.<br />

(b) Special provisions for the protection of the<br />

headerboard and adjacent rebar during construction may<br />

be necessary.<br />

f. Leave-Outs Temporary gaps in CRCPs should be avoided. The<br />

necessity for leave-outs is minimized by giving proper<br />

consideration to the paving schedule during project design. The<br />

following precautions can be specified to reduce distress in<br />

the leave-out portion of the slab in the event a leave-out does<br />

become necessary. '.<br />

(1) Leave-outs require 50 percent more longitudinal deformed<br />

bars of the same nominal size as the regular reinforcement.<br />

The additional reinforcement should be spaced evenly<br />

between every other normal <strong>pavement</strong> reinforcing bar and<br />

should be bonded at least 3 feet into the <strong>pavement</strong> ends<br />

adjacent to the leave-outs. All regular longitudinal<br />

reinforcement should extend into the leave-out a minimum of<br />

8 feet. Required slices should be made the same as those<br />

in normal construction.<br />

(2) Leave-outs should be paved during stable weather conditions<br />

when the daily temperature cycle is small. Because of the<br />

closeness of the steel extreme care should be exercised in<br />

placing and consolidating the concrete to prevent<br />

honeycombing or voids under the reinforcement<br />

3.6.9