24.03.2013 Views

chapter 3 rigid pavement - DOT On-Line Publications - Department ...

chapter 3 rigid pavement - DOT On-Line Publications - Department ...

chapter 3 rigid pavement - DOT On-Line Publications - Department ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

serve as a leveling course, to correct superelevation, and to serve as a<br />

bondbreaker to the 6-inch CRCP overlay. The 6-inch CRCP overlay uses<br />

15 deformed bars spaced at 8.5 inches (0.6 percent steel of the cross<br />

sectional area). Transverse steel (#4 bars) was spaced at 34 inches and<br />

tied underneath the longitudinal steel. The steel reinforcement was<br />

supported on metal chairs and the plans specified a cover tolerance of<br />

2 l/2 - 2 11/16 inches.<br />

The added 12-foot wide CRCP lane was placed on the outside of the overlay<br />

portion. The new lane is a g-inch CRCP on a &inch crushed granular base.<br />

It uses #5 deformed bars spaced at 5.5 inches (0.6 percent of the cross<br />

sectional area). Transverse steel (#4 bars) was spaced at 30 inches and<br />

tied underneath the longitudinal steel. The steel reinforcement was<br />

supported by metal chairs and the plans specified a cover tolerance of<br />

3 3/8 - 3 7/8 inches.<br />

The plans provided the option of constructing the added right lane with the<br />

overlay or separately with a keyway. State highway personnel, however,<br />

report the keyway construction joint was likely used. The plans indicate<br />

there are tie bars in the keyway but we are unable to determine their<br />

length or spacing.<br />

Traffic survey data gathered during the overlay design stage (1970)<br />

indicate ADT of 10,600-14,050; 12-13 percent trucks; projected 1991 ADT<br />

of 40,650-42,450; 12-13 percent trucks.<br />

An extensive soils investigation was conducted during the overlay design<br />

stage. A brief review of the soil boring tabulation indicated the presence<br />

of silt, and rock fragments occurring within the top 5 feet of roadbed in<br />

the location of the widened outer lane. Little information is available<br />

for the roadbed beneath the original <strong>pavement</strong>. Also, there is little<br />

information available concerning the condition of the original <strong>pavement</strong><br />

during design Cf the overlay.<br />

Three cores of the existing CRCP <strong>pavement</strong> were recently taken and a<br />

petrographic examination was conducted. An analysis of the cores is found<br />

in Section VI.<br />

A French drain was installed where the original roadway was in sag<br />

alignment and then daylighted to the reconstructed 6:l side slopes. State<br />

personnel have stated these are not presently functioning.<br />

The inside shoulder width is 4.0 feet. The outside shoulder is 10.0 feet.<br />

Each is a 3-inch thick bituminous ccncrete shd'ulder on a 7-inch dense-<br />

graded stabilized aggregate subbase. The shoulder joint was designed to be<br />

sealed with hot-poured, rubber-asphalt joint sealing compound.<br />

Personnel kho were present during the overlay construction projects<br />

reported that the -reject was shut dowh several times because of fines and<br />

clay balls in the 'ggregate. Also, th:-:-e were difficu;;ies in finishing<br />

the slab. The w .bound overlay (middie and high speed) lanes were placed<br />

in May-July perioa. The eastbound overlay lanes were placed in October and<br />

3.7.4

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!