Checklists<br />
Requirements to be Used<br />
(a) Periodic inspection and testing <strong>for</strong> a low voltage<br />
installation which was connected to supply:<br />
(i) be<strong>for</strong>e 1.1.1985 1<br />
(ii) on or after 1.1.1985 and be<strong>for</strong>e 1.6.1992 1 and 2<br />
(iii) on or after 1.6.1992 1, 2 and 3<br />
(b) Inspection and testing carried out upon completion <strong>of</strong> 1, 2, 3<br />
any electrical work <strong>for</strong> a low voltage installation and 4<br />
(2) Test sequence<br />
Where more than one <strong>of</strong> <strong>the</strong> checklists are to be used, <strong>the</strong> items to be<br />
tested should follow <strong>the</strong> sequence stated in <strong>Code</strong> 21B(2)(a). The records<br />
against <strong>the</strong> items <strong>of</strong> <strong>the</strong> checklists used do not indicate <strong>the</strong> test sequence.<br />
(3) Checklist <strong>for</strong> high voltage installations<br />
For high voltage installations that are required to be inspected, tested<br />
and certified at least once every year, records showing <strong>the</strong> results <strong>of</strong> <strong>the</strong><br />
items <strong>of</strong> inspection and testing per<strong>for</strong>med according to checklist<br />
numbered 5 in Appendix 13 are generally acceptable. Recommendation<br />
<strong>for</strong> testing <strong>of</strong> high voltage installations given in relevant recognised<br />
standards and manufacturers <strong>for</strong> commissioning and periodic tests,<br />
where appropriate, should also be used.<br />
(4) Content <strong>of</strong> checklists<br />
(a) The checklists given in Appendix 13 contain a number <strong>of</strong> important<br />
items to be recorded after an inspection and testing and <strong>the</strong>y are<br />
given to indicate generally <strong>the</strong> minimum requirements <strong>for</strong> record<br />
purposes only. The registered electrical worker carrying out <strong>the</strong><br />
inspections and tests should fill in test results and <strong>the</strong> rating <strong>of</strong> key<br />
items where indicated in <strong>the</strong> checklists; and must certify with date<br />
on each individual item <strong>of</strong> inspection and testing listed. The use <strong>of</strong><br />
initials <strong>for</strong> such certification is acceptable if a sample <strong>of</strong> <strong>the</strong> initial<br />
against a full signature <strong>of</strong> <strong>the</strong> registered electrical worker has been<br />
given in <strong>the</strong> records. Where any item listed in <strong>the</strong> checklists is not<br />
applicable to <strong>the</strong> installation under inspection and testing, <strong>the</strong><br />
registered electrical worker should also certify it to be so. The use <strong>of</strong><br />
<strong>the</strong> abbreviation ‘N/A’ is acceptable <strong>for</strong> this purpose. The registered<br />
electrical worker should also ensure that all o<strong>the</strong>r relevant inspection<br />