Pre-Application Consultation Report<br />
Consultee Consultee Comments and Feedback Action / Response Taken Further Information<br />
No. Type Date<br />
Received<br />
--<br />
Coriolis LLP Project Developer<br />
discussed at meeting of 10.12.09 and<br />
suggested would remain in contact in<br />
the future<br />
cut or removed to make vision easier leaving<br />
our property<br />
We would like you to consider improving the<br />
kids play area to the front of the house by<br />
landscaping and tree planting to shield traffic<br />
noise<br />
19. Meeting 10.12.09 Consultee Has plans for eco-house beside trout farm<br />
lake south of Moor Road. Problems with<br />
electric supply cost<br />
Suggest that local contractor available to do<br />
civils work and would not object to the<br />
Further information on the<br />
proposals will be provided<br />
in the ES<br />
Coriolis Energy LLP Project Developer<br />
met with consultee (Golf Club) in person<br />
on 10.11.09 to discuss the proposals<br />
proposals<br />
Following the public exhibition of 20.10.09 the<br />
Golf Club made contact with Coriolis Energy LLP<br />
Project Developer to request a meeting/<br />
presentation<br />
20. Email Ongoing Nearby Golf Club<br />
1<br />
Latest proposed windfarm layout was<br />
delivered by hand to the Golf Club on<br />
10.12.09<br />
Response to queries from Golf Club<br />
(received 15.12.09) sent by email on<br />
07.01.10:<br />
1. Scoping Report was submitted to<br />
ERC Planning Department in<br />
September 2008. A Scoping Opinion<br />
Letter was received from ERC Roads,<br />
Planning and Transportation Service on<br />
26 November 2008.<br />
2. Planning to submit the application to<br />
the ERC Roads, Planning and<br />
Transportation Service early in 2010.<br />
3. In the design layout provided by<br />
Project Developer to the Golf Club in<br />
early December 2009, which may be<br />
subject to change, the nearest turbine is<br />
Email of 15.12.09<br />
1 When will the scoping opinion be applied for<br />
and when will it be published?<br />
2 When do you plan to make your application to<br />
the planning authority?<br />
3 How close to the golf course will the nearest<br />
turbines be?<br />
4 What turbines will you be using? Will they be<br />
unnamed, so as to give you a competitive<br />
advantage when bidding or are you naming<br />
candidate turbines now? What will their overall<br />
height be?<br />
5 What is the precise intended layout?<br />
6 Noise is evident from many windfarms at<br />
±750m. May we see your noise predictions?<br />
7 Have you carried out bird and wildlife studies?<br />
If so can we see them, and if not are you going to<br />
do so?<br />
Natural Capital Ltd 27 Falck Renewables