Photo 2:<br />

Pulogadung – Flamboyan<br />

(Mediros Hospital)<br />

There<strong>for</strong>e, the traffic uses mostly two lanes. The <strong>BRT</strong> lanes can be implemented while<br />

maintaining the actual capacity <strong>for</strong> mixed traffic if:<br />

o The sidewalks are reconstructed and preserved only as a walk way.<br />

o Parking and other uses on the first lane are <strong>for</strong>bidden and controlled (this means<br />

permanent policeman allocated to patrol this section)<br />

If the above cannot be implemented, it is recommended not to implement <strong>BRT</strong> exclusive<br />

lanes on this 1.2 km section, just use the left lane as a normal lane, shared by <strong>BRT</strong> and<br />

general traffic.<br />

Directional traffic goes up to 2400 pcu/hour. According to the standard of 400<br />

pcu/meter, the general traffic would need only 2400/420 = 5.6 meters.<br />

In the near future, volume could increase by 30% and there<strong>for</strong>e the general traffic would<br />

need 7.4 meters.<br />

However, there is not enough space to provide 7.4 meters <strong>for</strong> the general traffic. The<br />

existing space of 5.6 meter is only enough <strong>for</strong> the present volume, so we suggest Jakarta<br />

government to acquire land to obtain a wider section.<br />

VI.4.a.ii. DisHub and <strong>ITDP</strong> Proposed Typical <strong>TransJakarta</strong> Cross Sections<br />

Presently, <strong>for</strong> the first 100 meters from Pulo Gadung terminal, there is a signalized right<br />

turn conversion from west to enter south to the terminal, and boarding and alighting on<br />

buses and associated street vendors on this section is very intensive. If the <strong>BRT</strong> were<br />

implemented, saturation degree would be above 100% and considerable congestion will<br />

occur on peak periods. While bus lane <strong>for</strong> this segment would certainly give a big travel<br />

Final Recommendations <strong>for</strong> <strong>TransJakarta</strong>, p. 97