Audited Financial Information<br />

(` lakhs)<br />

Particulars March 31, 2010 March 31, 2009 March 31, 2008<br />

Sales 2,097.03 1,269.30 206.00<br />

Other Income 10.49 6.35 1.03<br />

Net Profit 8.11 5.64 0.74<br />

Share <strong>Capital</strong><br />

- <strong>APR</strong>CL 11.20 4.89 0.66<br />

- MVR 3.73 1.63 0.20<br />

Loans Funds Nil Nil Nil<br />

2. <strong>APR</strong>CL – PVRPL (JV)<br />

Our Company has entered into a Joint Venture Agreement dated November 27, 2008 with M/s PVR Projects <strong>Limited</strong><br />

pursuant to which joint venture entity <strong>APR</strong>CL-PVRPL (JV) (in proportion of 50:50) has been formed for the purpose<br />

of bidding and execution of “Package No. 1/2008-09 – Major Irrigation – Nellore District – Modernization of Pennar<br />

Delta System – Investigation, Designs, Drawings, Estimation and Construction of all the following works duly getting<br />

approval from the competent authority including Repairs/Reconstruction of all existing structures. New Construction<br />

on the above Channel including Maintenance of the same for a period of two years after completion of work etc.,<br />

a. Providing lining in cement concrete to 26 Distributaries and Minors of Southern Channel System<br />

b. Providing lining in cement concrete to 26 Distributaries and Minors of Eastern Channel and Allur Tank<br />

supply Channel System<br />

c. Providing lining in cement concrete to 38 Distributaries and Minors of Jaffersaheb Canal System<br />

d. Providing lining in cement concrete to 34 Distributaries and Minors of Survepalli Canal System”<br />

The JV has received the Irrigation and CAD Department, Nellore vide letter dated February 02, 2009. The said joint<br />

venture has entered in to a sub-contracting agreement dated April 02, 2009 with our Company whereby 50% of the<br />

project was sub-contracted to our Company for a royalty of 0.10% on the gross bills.<br />

Audited Financial Information<br />

(` lakhs)<br />

Particulars March 31, 2010 March 31, 2009 March 31, 2008<br />

Sales 906.73 0.00 0.00<br />

Other Income 0.91 0.00 0.00<br />

Net Profit 0.44 0.00 0.00<br />

Share <strong>Capital</strong><br />

- <strong>APR</strong>CL 0.49 0.00 0.00<br />

- PVRPL 0.22 0.00 0.00<br />

Loans Funds Nil Nil Nil<br />

3. <strong>APR</strong>CL - CRSSG (JV)<br />

Our Company has entered into a Joint Venture Agreement dated March 21, 2007 with M/s China Railway Shisiju<br />

Group Corporation (CRSSG), pursuant to which joint venture entity <strong>APR</strong>CL-CRSSG (JV) (in proportion of<br />

75:25) has been formed for bidding and execution of<br />

carrying out “Package No.08/06: Investigation, designs, excavation and lining of Balaji Tunnel-I of GNSS<br />

main canal from Km 240.0 to 254.00 including all allied works under GNSS Project Phase –II in Kadapa<br />

District.”<br />

for carrying out “Package No.09/06: Investigation, design and 1) Earthwork, excavation of GNSS Main<br />

Canal from Km 254.000 to 264.000 including construction of CM & CD works and 2) Excavation and lining<br />

of Balaji Tunnels – II from Km 264.000 to Km 275.000 including all allied works under GNSS in Chittor<br />

District.”<br />