30.01.2015 Views

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Anderson Engineers, P.A.<br />

12041 – <strong>ROSEMARY</strong> <strong>BEACH</strong> OWNER’S CENTER<br />

C. Units shall be laid to preserve vertical continuity of cells to be filled. The vertical alignment shall be<br />

sufficient to maintain a clean, unobstructed flue measuring not less than 3"x3". Place no units or cut<br />

pieces of masonry less than 4" nominal.<br />

D. In placing mortar in horizontal joints, completely cover the face shells of each unit with mortar. Solidly fill<br />

all head joints to the thickness of the face shell and shove units tightly in place. Solidly bed in mortar all<br />

head and cross web bed joints adjacent to cells to be grouted to prevent leakage of mortar.<br />

E. Lay designated walls in two separate wythes, with insulated cavity as indicated.<br />

F. Anchor and bond intersecting masonry walls with 50% masonry bond, except as noted otherwise on<br />

drawings.<br />

G. Install precast and/or composite steel lintels over all openings. Set lintels in place with joints pointed to<br />

match adjacent work. Build in lintels, reinforce and fill with structural concrete grout as work progresses.<br />

1. Steel lintels shall be provided with 3" minimum structural bearing each side of openings.<br />

2. Pre-cast concrete lintels shall be provided with 8" minimum structural bearing each side of<br />

openings.<br />

3. Typical steel and cut masonry lintels, even if not shown on structural or architectural drawings,<br />

shall be reinforced with a minimum of 1 #5 bar continuous (extend 12" minimum each end) and<br />

grouted solid.<br />

4. Concrete masonry work shall not proceed beyond the elevation of door and window headers<br />

until all vertical reinforced cells and reinforced horizontal lintels have been grouted.<br />

H. At hard tile locations take extra care in laying units such that wall will be suitable for thinset tile installation<br />

directly to wall. Grind any unevenness judged unacceptable by ARCHITECT.<br />

I. Install wall control/expansion joints at 20 ft. o.c. and/or as shown and detailed on<br />

architectural/engineering drawings. Refer to Sections 04000/Masonry, General and 07920/Sealants,<br />

Caulking and Seals for additional requirements.<br />

3.04 CUTTING<br />

A. Do all cutting of block with carborundum or equivalent saw. To facilitate proper coursing, half blocks may<br />

be used to reduce amount of cutting. No masonry will be permitted to be used if not cut properly.<br />

Masonry broken by "blows" will be replaced, even if found after the wall has been completed.<br />

3.05 PLACING STEEL REINFORCEMENT<br />

A. Reinforcing steel to be straight, except for bends around corners and as detailed otherwise on drawings.<br />

Lap reinforcing steel 48 bar diameters minimum. Place vertical bars in exact center of cells, or as<br />

otherwise indicated, and hold in position at top and bottom and at intervals not to exceed 96 bar<br />

diameters. Vertical cavity rebar to be run in maximum possible lengths, 5'-0" minimum, using low lift<br />

grouting procedures.<br />

B. Completely embed joint reinforcement in mortar or grout. Lap splices 6 inches minimum at all locations.<br />

C. Lap dowels in footings to vertical steel in masonry columns by placing in aligned cells, then grouting cells<br />

to obtain bonded lap between wall and footings.<br />

D. Reinforce and grout all reinforced horizontal block courses, as wall is built-up.<br />

3.06 DOUBLE WYTHE MASONRY CAVITY WALL INSULATION<br />

CONCRETE MASONRY 042000-3

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!