SECTION 00 73 80 - WEATHER DELAY LOG<br />

A. Project:<br />

12041 Rosemary Beach Owners Center, rosemary Beach, FL.<br />

B. Date:<br />

C. Weather Event:<br />

D. Work On Progress:<br />

E. Is the work on the Critical Path<br />

F. Length of Delay:<br />

G. If the work is not on the Critical Path, how many days of delay until this work<br />

category will be on the Critical Path<br />

Instructions:<br />

1. The above information is required to be submitted with each payment request on a<br />

monthly basis. The NOA weather report and superintendents daily log must be<br />

submitted with weather extension request.<br />

2. This information will be required as back-up to grant a Time Extension request for delays<br />

caused by weather events.<br />

3. Direct delays for work stoppages that are on the critical path will be given accordingly.<br />

4. Delays for work not on the critical path shall be logged and delay logs for that category<br />

of work shall be accumulated and submitted in the event the work enters the critical<br />

patch and causes a delay of the project.<br />

5. Delays will be granted only on the basis of adverse effect on the Critical Path of work for<br />

the project.<br />

References:<br />

CONTRACT FOR CONSTRUCTION, EXHIBIT C, DIVISION 1 (CONTRACT)<br />

8. Any time or day lost to a weather related delay including wet ground conditions, rain, other<br />

forms of precipitation, and cold weather conditions, shall be an extension to the construction<br />

time regardless whether the period is under normal or adverse weather conditions.<br />

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION – A201<br />

Article 4.3.7.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim<br />

shall be documented by data substantiating that weather conditions were abnormal for the period of<br />

time, could not have been reasonably anticipated and had an adverse effect on the scheduled<br />

construction.<br />

Submitted by:<br />

Signature:<br />

General Contractor:<br />

WEATHER DELAY LOG 00 73 80 -1