30.01.2015 Views

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

2013 4 29 ROSEMARY BEACH PROJECT MANUAL.pdf

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

DAG Architects Inc<br />

12041 Rosemary Beach Owners Center<br />

Rosemary Beach, FL.<br />

.2 For the Contractor, for Work performed by the Contractor’s Subcontractor, a maximum of<br />

seven and one-half percent (7-1/2%) of the amount due the Subcontractor.<br />

.3 For each Subcontractor or Sub-subcontractor involved, for Work performed by that<br />

Subcontractor’s or Sub-subcontractor’s own forces, a maximum of fifteen percent (15%) of<br />

the cost.<br />

.4 For each Subcontractor for work performed by the Subcontractor’s Sub-subcontractors, a<br />

maximum of seven and one-half percent (7-1/2%) of the amount due the Subsubcontractors.<br />

.5 Cost to which overhead and profit is to be applied shall be determined in accordance with<br />

Subparagraph 7.3.6.<br />

.6 In order to facilitate checking of quotations for extras or credits, all proposals, except those<br />

so minor that their propriety can be seen by inspection, shall be accompanied by a<br />

complete itemization of costs including labor, materials and subcontracts. Labor and<br />

materials shall be itemized in the manner prescribed above. Where major cost items are<br />

subcontracts, they shall be itemized also. In no case will a charge over $100.00 be<br />

approved without such itemization.<br />

ARTICLE 8; TIME<br />

8.2 PROGRESS AND COMPLETION<br />

Add the following Subparagraph 8.2.4 and 8.2.5 to 8.2:<br />

8.2.4 The work to be performed under the Contractor’s Base Proposal as defined in the Contract<br />

Documents shall be substantially completed by ________________________.<br />

8.2.5 Failure to complete the Project within the time fixed in this Agreement will result in substantial injury<br />

to the Owner, and as damages arising from such failure cannot be calculated with any degree of<br />

certainty, according to the definition of “ Substantial Completion” in Subparagraph 9.8.1 of the<br />

General Conditions, within the time fixed or within such further time, if any, as maybe authorized in<br />

accordance with Contract Documents, the Contractor shall pay to the Owner as Liquidated Damages<br />

for such delay, and not as a penalty, $500.00 for each and every calendar day elapsing between the<br />

date fixed for Substantial Completion and the date such Substantial Completion shall bee fully<br />

accomplished. It is also hereby agreed that if after thirty (30) Calendar days after Substantial<br />

Completion this Project is not fully and finally completed in accordance with the requirements of the<br />

Contract Documents, the Contractor shall pay to the Owner as Liquidated Damages, and not as a<br />

penalty, for such delay, 1/4 of the rate previously indicated. These Liquidated Damages shall be<br />

payable in addition to any expenses or costs payable by the Contractor to the Owner under the<br />

provision of the Contract Document and shall not exclude the recovery of damages of te Owner<br />

under the Contract Documents.<br />

This provision of Liquidated Damages for delay shall in no manner affect the Owner’s right to<br />

terminate the Contract. The Owner’s exercise of the right to terminate shall not release the<br />

Contactor from his obligation to pay Liquidated Damages.<br />

It is further agreed that the Owner may deduct from the balance of the Contract Sum held by the<br />

Owner the Liquidated Damages stipulated herein or such portions, as said balance will cover.<br />

8.3 DELAYS AND EXTENSIONS OF TIME<br />

Add the following Clause 8.3.1.1 to Subparagraph 8.3.1:<br />

SUPPLEMENTARY CONDITIONS OF THE CONTRACT FOR CONSTRUCTION 00 73 00 -9

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!