DAG Architects Inc.<br />

12041 Rosemary Beach Owners Center<br />

Rosemary Beach Fl.<br />

3.8.2 Install floor drains at low points of surface areas to be drained, or as indicated. Set tops of drains<br />

flush with finished floor.<br />

3.8.3 Install drain flashing collar or flange so that no leakage occurs between drain and adjoining<br />

flooring. Maintain integrity of waterproof membranes, where penetrated.<br />

3.8.4 Position drains so that they are accessible and easy to maintain.<br />

3.9 Connection of Trap Primers: Connect trap primers as indicated, and in accordance with<br />

manufacturer's installation instructions. Pitch piping towards drain trap, minimum of 1/8" per foot<br />

(1%). Adjust trap primer for proper flow.<br />

3.10 Piping Runouts to Fixtures: Provide soil and waste piping runouts to plumbing fixtures and<br />

drains, with approved trap, of sizes indicated, but in no case smaller than required by Florida<br />

Building Code-Plumbing.<br />

3.11 Test, clean, flush, and inspect soil and waste piping in accordance with requirements of Division-<br />

22 Basic Plumbing Materials and Methods section "Testing, Cleaning and Sterilization of Piping<br />

Systems".<br />

END OF SECTION 22 13 16<br />

SOIL, WASTE, AND VENT SYSTEM 22 13 16 - 4/4