DAG Architects Inc<br />

12041 Rosemary Beach Owners Center<br />

Rosemary Beach, FL.<br />

progress schedule, the Contractor shall take such steps as may be necessary to improve the<br />

progress by increasing the number of shifts, overtime operations, days of work and the amount of<br />

construction plans, all without additional cost to the Owner.<br />

3.3.5 The Contractor shall not be relieved of obligations to perform the Work in accordance with the<br />

Contract Documents either by activities or duties of the Architect in the Architect’s administration of<br />

the Contract, or by tests, inspections or approvals required or performed by persons other than the<br />

Contractor.<br />

3.3.6 The Contractor shall furnish sufficient forces, construction plant and equipment, and shall work such<br />

hours, including night shifts and overtime operations, as may be necessary to insure the prosecution<br />

of the Work in accordance with the approved progress schedule. If the Contractor falls behind the<br />

progress schedule, the Contractor shall take such steps as may be necessary to improve the<br />

progress by increasing the number of shifts, overtime operations, days of work and the amount of<br />

construction plant, all without additional cost to the Owner.<br />

3.3.7 Failure of the Contractor to comply with the requirements under this provision shall be grounds for<br />

determination by the Architect that the Contractor is not executing the Work with such diligence as<br />

will insure completion within the time specified and such failure may constitute a substantial<br />

violation of the conditions of the Agreement.<br />

3.3.8 Upon such determination, the Owner may terminate the Contractor’s right to proceed with the<br />

Work, or any separable part thereof, in accordance with Article 14 of the General Conditions, or may<br />

with hold further payments as indicated in Article 9.5.1 also of the General Conditions.<br />

3.4 LABOR AND MATERIALS<br />

Add the following Subparagraphs 3.4.4, 3.4.5, 3.4.6 and 3.4.7 to 3.4:<br />

3.4.4 After the Contract has been executed, the Owner and the Architect will consider a formal request for<br />

the substitution of products in place of those specified only under the conditions set forth in the<br />

General Requirements (Division 1 of the Specifications), Section “Product Requirements.”.<br />

3.4.5 By making requests for substitutions based on Subparagraph 3.4.4 above, the Contractor:<br />

1. Represents that the Contractor has personally investigated the proposed substitute product<br />

and determined that it is equal or superior in all respects to that specified;<br />

2. Represents that the Contractor will provide the same warranty for the substitution that the<br />

Contractor would for that specified;<br />

3. Certifies that the cost data presented is complete and includes all related costs under this<br />

Contract, including the Architect's or Engineer’s redesign costs, and waives all claims for<br />

additional costs related to the substitution which subsequently become apparent; and<br />

4. Will coordinate the installation of the accepted substitute, making such changes as may be<br />

required for the Work to be complete in all respects.<br />

3.4.6 The Contractor shall follow all specified and manufacturer’s standards for Delivery, Storage and<br />

Handling of all products. All products that require storage in a climate-controlled environment shall<br />

be so handled. In all cases the more stringent guidelines shall be followed.<br />

3.4.7 The Contractor shall follow all specified and manufacturers instructions and conditions for installation<br />

SUPPLEMENTARY CONDITIONS OF THE CONTRACT FOR CONSTRUCTION 00 73 00 -3