DAG Architects Inc<br />

12041 Rosemary Beach Owners Center<br />

Rosemary Beach, FL.<br />

9.3 APPLICATIONS FOR PAYMENT<br />

Add the following subparagraph 9.3.1.4 to 9.3:<br />

9.3.1.4 The full Contract retainage may be reinstated if the manner of completion of the Work and its<br />

progress do not remain satisfactory to the Architect (or if the Surety withholds its consent), or for<br />

other good and sufficient reasons.<br />

9.4 CERTIFICATES FOR PAYMENT<br />

Add the following paragraphs:<br />

9.4.3 The Architect shall certify a payment of ninety percent (90%) of the value of the Work and materials<br />

as above noted according to his best judgment of the correct amount.<br />

9.4.4 On these monthly certificates, ten percent (10%) of the total of the estimated work for that month<br />

shall be retained until completion and acceptance of the job.<br />

9.4.5 Upon substantial completion of the job, the Architect may issue a semi-final certificate covering<br />

payment up to ninety percent (90%) of the Contract Sum less any reserves to cover any incomplete<br />

items.<br />

9.7 FAILURE OF PAYMENT<br />

Add the following article to 9.7:<br />

9.7.2 PAYMENTS TO SUBCONTRACTORS<br />

9.7.2.1 If the Architect fails to issue a Certificate for Payment for any cause which is the fault of the<br />

Contractor and not the fault of a particular Subcontractor, the Contractor shall pay that<br />

Subcontractor on demand, made at any time after the Certificate for Payment should otherwise<br />

have been issued for his work to the extent completed, less the retained percentage.<br />

9.7.2.2 The Contractor shall pay each Subcontractor a just share of any insurance moneys received by the<br />

Contractor under Article 11, and he shall require each Subcontractor to make payments to his<br />

subcontractors.<br />

9.7.2.3 The Architect will, on request, furnish to a Subcontractor, if practicable, information regarding<br />

percentages of completion or amounts applied for by the Contractor and action taken thereon by<br />

the Architect and Owner on account of portions of the Work done by such Subcontractor.<br />

9.7.2.4 Neither the Owner nor the Architect shall have any obligation to pay or to see the payments of any<br />

moneys to any Subcontractor except as may otherwise be required by Florida Statutes. Payment to<br />

material suppliers shall be treated in a manner similar to that provided in Subparagraphs 9.7.2.1, 2,<br />

and 3.<br />

10.6 EMERGENCIES<br />

SUPPLEMENTARY CONDITIONS OF THE CONTRACT FOR CONSTRUCTION 00 73 00 -11