09.12.2022 Views

Operations and Supply Chain Management The Core

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

132 OPERATIONS AND SUPPLY CHAIN MANAGEMENT

exhibit 5.3

Work Breakdown Structure, Large Optical Scanner Design

Level

1 2 3 4

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

x

1

1.1

1.1.1

1.1.2

1.1.3

1.1.4

1.2

1.2.1

1.2.1.1

1.2.1.2

1.2.2

1.2.3

1.2.4

1.3

1.4

1.4.1

1.4.2

1.5

1.5.1

1.5.2

1.6

1.6.1

1.6.2

1.6.3

Optical simulator design

Optical design

Telescope design/fab

Telescope/simulator optical interface

Simulator zoom system design

Ancillary simulator optical component specification

System performance analysis

Overall system firmware and software control

Logic flow diagram generation and analysis

Basic control algorithm design

Far beam analyzer

System inter- and intra-alignment method design

Data recording and reduction requirements

System integration

Cost analysis

Cost/system schedule analysis

Cost/system performance analysis

Management

System design/engineering management

Program management

Long lead item procurement

Large optics

Target components

Detectors

Activities

Pieces of work

within a project that

consume time. The

completion of all the

activities of a project

marks the end of the

project.

LO5–2 Evaluate

projects using

earned value

management.

Gantt chart

Shows in a graphic

manner the amount

of time involved and

the sequence in

which activities can

be performed. Often

referred to as a bar

chart.

There is not a single correct WBS for any project, and two different project teams might

develop different WBSs for the same project. Some experts have referred to project management

as an art rather than a science, because there are so many different ways that a

project can be approached. Finding the correct way to organize a project depends on experience

with the particular task.

Activities are defined within the context of the work breakdown structure and are

pieces of work that consume time. Activities do not necessarily require the expenditure of

effort by people, although they often do. For example, waiting for paint to dry may be an

activity in a project. Activities are identified as part of the WBS. From our sample project

in Exhibit 5.3, activities would include telescope design and fabrication (1.1.1), telescope/

simulator optical interface (1.1.2), and data recording (1.2.4). Activities need to be defined

in such a way that when they are all completed, the project is done.

MANAGING PROJECTS

We now look at how projects are actually managed while they are being completed. Charts

and various types of standard forms are useful because their visual presentation are easily

understood. Computer programs are available to quickly generate the charts, and we discuss

these later in the chapter.

Exhibit 5.4A is a sample Gantt chart, sometimes referred to as a bar chart, showing

both the amount of time involved and the sequence in which activities can be performed.

The chart is named after Henry L. Gantt, who won a presidential citation for his application

of this type of chart to shipbuilding during World War I. In the example in Exhibit 5.4A,

“Long lead procurement” and “Manufacturing schedules” are independent activities and

can occur simultaneously. All other activities must be done in the sequence from top to

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!